Review Details: PIA RESUBMITTAL
Plan Number - T07PI00044
Review Name: PIA RESUBMITTAL
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
01/22/2008 | SMONTIE1 | UTILITY CLEARANCES | COT STREETS DIVISION | Completed | Please submit utility clearance letters for El Paso Natural Gas, and Kinder Morgan Energy. Even if not applicable, need sheet showing N/A . |
01/22/2008 | SMONTIE1 | UTILITY CLEARANCES | COT WATER NEW DEVELOPMENT | Completed | Please submit utility clearance letters for El Paso Natural Gas, and Kinder Morgan Energy. Even if not applicable, need sheet showing N/A . |
01/22/2008 | SMONTIE1 | UTILITY CLEARANCES | PC WASTEWATER MGMT | Completed | Please submit utility clearance letters for El Paso Natural Gas, and Kinder Morgan Energy. Even if not applicable, need sheet showing N/A . |
01/22/2008 | SMONTIE1 | UTILITY CLEARANCES | QUEST COMMUNICATION | Completed | Please submit utility clearance letters for El Paso Natural Gas, and Kinder Morgan Energy. Even if not applicable, need sheet showing N/A . |
01/22/2008 | SMONTIE1 | UTILITY CLEARANCES | TUCSON ELECTRIC POWER CO | Completed | Please submit utility clearance letters for El Paso Natural Gas, and Kinder Morgan Energy. Even if not applicable, need sheet showing N/A . |
01/22/2008 | SMONTIE1 | UTILITY CLEARANCES | COX COMMUNICATION | Completed | Please submit utility clearance letters for El Paso Natural Gas, and Kinder Morgan Energy. Even if not applicable, need sheet showing N/A . |
01/22/2008 | SMONTIE1 | UTILITY CLEARANCES | SOUTHWEST GAS CORP | Completed | Please submit utility clearance letters for El Paso Natural Gas, and Kinder Morgan Energy. Even if not applicable, need sheet showing N/A . |
01/24/2008 | SMONTIE1 | UTILITY CLEARANCES | EL PASO NATURAL GAS | Completed | Please submit utility clearance letters for El Paso Natural Gas, and Kinder Morgan Energy. Even if not applicable, need sheet showing N/A . |
01/24/2008 | SMONTIE1 | UTILITY CLEARANCES | KINDER MORGAN ENERGY | Completed | Please submit utility clearance letters for El Paso Natural Gas, and Kinder Morgan Energy. Even if not applicable, need sheet showing N/A . |
02/07/2008 | THAD HARVISON | DOT ENGINEERING | REVIEW | Approv-Cond | Plan No reads S04-053 on pages 4 and 5. Change number to read D-2007-003. |
02/11/2008 | LANCE PETERSON | DOT STREET MAINTENANCE | REVIEW | Approv-Cond | We have reviewed this plan and approve it under the following condition: 1. Sheet 2 - At the loading area, it appears that there may be a ponding problem. Please make sure that there is adequate fall in the gutter line to convey the runoff to the east. No further comments. |
02/12/2008 | JOSE ORTIZ | DOT TRAFFIC | REVIEW | Approved | |
02/14/2008 | SMONTIE1 | PIA COORDINATOR | CUSTOMER CALLED; PLANS @ AMBASSADOR | Completed | |
02/14/2008 | SMONTIE1 | PIA COORDINATOR | OUT TO CUSTOMER | Completed |