Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Plan Review Detail
Review Status: Completed
Review Details: PIA RESUBMITTAL
Plan Number - T07PI00031
Review Name: PIA RESUBMITTAL
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 04/20/2009 | LANCE PETERSON | DOT STREET MAINTENANCE | REVIEW | Approved | We have reviewed this plan and have the following comments: 1. Sheet 3 fo 5, STA 16+75 - This area shows rip rap but does not have a D-50 and a thickness. Also the rip rap needs to be placed over a filter fabric. 2. Sheet 4 of 5, STA 15+10 - This area calls out a new scupper but does not show any erosion control at the back of the scupper. Please call out the D-50 and thickness of the material. Also, this should be placed over filter fabric. 3. - Sheet 5 of 5 - Rip rap is called out but typically the thickness is 2 times D50. Please verify what you have called out is adequate. Also, the rip rap should be placed over filter fabric. No further comments. |
| 04/20/2009 | LANCE PETERSON | DOT STREET MAINTENANCE | REVIEW | Approved | No objection pertaining to Street Maintenance. 10/26/2009 |
| 04/23/2009 | RICHARD LEIGH | DOT ENGINEERING | REVIEW | Denied | April 21, 2009 Project: Red Colt Ranch, 22nd St and Red Colt Road, PIA Plan T07PI0007 PROJECT REVIEWER: Richard Leigh, Senior Engineering Associate Permits and Codes Section RESUBMITTAL REQUIRED: Permits and Codes Section has reviewed the PIA Plan and does not recommend approval of the PIA Plan at this time. The following comments need to be addressed in the next submittal. 1. Submit Geotechnical Report supporting the proposed pavement structural sections for Red Colt Road. 2. Sheet 5, Details B and C: Indicate the existing pavement structure. The proposed pavement structure must match or exceed the existing pavement structure. 3. Provide a detail for each type of proposed curb access ramp. Indicate the use of truncated domes as the tactile warning device. 4. Show all existing roadway infrastructures and indicate when joining new to existing. Additionally, provide stationing and call out any applicable standard details. 5. Sheet 5, Scupper Plan Detail: Detail of the scupper is inaccurately depicted. Top plate must extend to face of curb and wedge curb must transition to vertical to curb to where it meets scupper. Refer to PC/COT standard Detail 205 for additional details. 6. Sheet 5: The inside curb radius should be parallel to the property line radius for the curb knuckle on Red Colt Road. 7. Provide a 50 ' long pavement transition from edge of existing pavement to new face of curb on 22nd Street. Provide stationing and offsets. 8. Show and label all existing utility infrastructure (poles, cabinets pull boxes, etc.) within the public right-of-way and indicate as to there disposition if enchroacing. 9. Check and verify construction notes. Some notes are inaccurately referenced. 10. Refer to redline plans for additional comments and comment details. If you have any questions, I can be reached at 837-6647 or Richard.Leigh@tucsoz.gov |
| 04/28/2009 | JOSE ORTIZ | DOT TRAFFIC | REVIEW | Denied | April 28, 2007 ACTIVITY NUMBER: T07PI00031 PROJECT NAME: Red Colt Ranch PROJECT ADDRESS: 9941 E 22ND ST PROJECT REVIEWER: Jose E. Ortiz PE, Traffic Engineer Resubmittal Required: Traffic Engineering does not recommend approval of the PIA Plan; therefore a revised PIA Plan is required for re-submittal. The following items must be revised or added to the plan. 1. Include a response letter with the next submittal that states how all comments have been addressed. 2. See redlines on the submitted drawings and address the additional redline comments. During the next submittal please re-submit the roll of redlines for back checking purposes. If you have any questions, I can be reached at 791-4259 x76730 or Jose.Ortiz@tucsonaz.gov |
| 05/22/2009 | TAMI HAUSER | PIA COORDINATOR | CUSTOMER CALLED; PLANS @ AMBASSADOR | Completed | |
| 05/22/2009 | TAMI HAUSER | PIA COORDINATOR | OUT TO CUSTOMER | Completed |