Plan Review Detail
Review Status: Completed
Review Details: PIA SUBMITTAL
Plan Number - T07PI00017
Review Name: PIA SUBMITTAL
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
06/08/2007 | ASHOFFS1 | UTILITY CLEARANCES | COT STREETS DIVISION | Denied | Please submit Utility Clearance Letters. |
06/08/2007 | ASHOFFS1 | UTILITY CLEARANCES | COT WATER NEW DEVELOPMENT | Denied | Please submit Utility Clearance Letters. |
06/08/2007 | ASHOFFS1 | UTILITY CLEARANCES | PC WASTEWATER MGMT | Denied | Please submit Utility Clearance Letters. |
06/08/2007 | ASHOFFS1 | UTILITY CLEARANCES | QUEST COMMUNICATION | Denied | Please submit Utility Clearance Letters. |
06/08/2007 | ASHOFFS1 | UTILITY CLEARANCES | TUCSON ELECTRIC POWER CO | Denied | Please submit Utility Clearance Letters. |
06/08/2007 | ASHOFFS1 | UTILITY CLEARANCES | COX COMMUNICATION | Denied | Please submit Utility Clearance Letters. |
06/08/2007 | ASHOFFS1 | UTILITY CLEARANCES | SOUTHWEST GAS CORP | Denied | Please submit Utility Clearance Letters. |
06/08/2007 | ASHOFFS1 | UTILITY CLEARANCES | EL PASO NATURAL GAS | Denied | Please submit Utility Clearance Letters. |
06/08/2007 | ASHOFFS1 | UTILITY CLEARANCES | KINDER MORGAN ENERGY | Denied | Please submit Utility Clearance Letters. |
06/22/2007 | JOSE ORTIZ | DOT TRAFFIC | REVIEW | Denied | June 21, 2007 ACTIVITY NUMBER: T07PI00017 PROJECT NAME: Tres Pueblos Norte PROJECT ADDRESS: 2364 E Drexel Rd PROJECT REVIEWER: Jose E. Ortiz PE, Traffic Engineer Resubmittal Required: Traffic Engineering does not recommend approval of the PIA Plan; therefore a revised PIA Plan is required for re-submittal. The following items must be revised or added to the plan. 1. Include a response letter with the next submittal that states how all comments have been addressed. 2. See redlines on the submitted drawings and address the additional redline comments. During the next submittal please re-submit the roll of redlines for back checking purposes. 3. At the Drexel Rd/Camino Malcote intersection reduce the lane widths along Drexel to 11' to minimize the eastbound taper offset along Drexel Rd. This is in an effort to reduce the abrupt change in alignment to eastbound motorists due to the short eastbound taper for the addition of the left turn lane. 4. Install an R6-1(R) "ONE WAY" Sign in the median along Tucson Blvd per PCDOT & TDOT Signing Manual (2002) Chap 9-3A. 5. Install R1-1 street names with the proposed stop signs at the proposed roadways entering this development off of Drexel Rd, & Tucson Blvd per PCDOT & TDOT Signing Manual (2002) Chap 5-11, 5-12, and Chap 9-2. 6. Place the PIA Case number on the cover sheet. If you have any questions, I can be reached at 791-4259 x76730 or Jose.Ortiz@tucsonaz.gov |
06/22/2007 | RICHARD LEIGH | DOT ENGINEERING | REVIEW | Denied | June 21, 2007 Tres Pueblos Norte, PIA Plan T07PI00017 PROJECT REVIEWER: Richard Leigh, TDOT, Permits and Codes Section RESUBMITTAL REQUIRED: Permits and Codes Section has reviewed the PIA Plan and does not recommend approval of the PIA Plan at this time. The following comments need to be addressed in the next submittal. 1. Include Book and Page on cover sheet. (Reminder). 2. Provide the administrative address on the cover sheet 3. Include the plan number "I-2007-024" in the title block of each sheet. 4. Include DSD activity number "T07PI00017"on cover sheet. 5. Verify that that all detail references refer to correct details. 6. Sheet 2: Identify dashed lines shown in the plan view at Sta. +/- 12+97 (Camino Malcote). 7. Sheet 2: The minimum desirable vertical curve length for vehicle travel lanes is 100'. 8. Sheet 6, Detail "F"; Barricade railing is not required on the roadway side of sidewalk scupper if the height of the scupper less than 12". 9. The proposed pavement structural section for Drexel Road must match existing. Indicate thickness of leveling and surfacing courses, mix designations and percentages of effective air voids in pavement structural section. 10. Refer to redline plans for additional comments and details. |
06/29/2007 | GARY WITTWER | DOT LANDSCAPE | REVIEW | Denied | 1. Please submit a copy of your approved NPPO plan. I am looking to see that any plants removed from the ROW have been included in the original inventory. 2. Please submit your approved landscape and irrigation plans for all common areas. I am looking to see if you have any private irrigation lines running under public roadways. Once the project is accepted, the roads become public. Because of Blue Stake law, no private irrigation lines will be permited under public roads. |
06/29/2007 | LANCE PETERSON | DOT STREET MAINTENANCE | REVIEW | Denied | We have reviewed this plan and have the following comments: 1. Sheet 3 - The plan shows the roadwork detail as A/5 , and this should be A/6. 2. Sheet 6 - Detail F - What will be the rock size and thickness of the rip rap pad? Also include filter fabric. 3. Sheet 6 - Detail E - Again, what will be the rock size and mat thickness of the rip rap? Also include filter fabric. 4. Will there be any landscaping insatlled with this project? If so, please submit the plan to Paul Rosenboom at 4004 S. Park Avenue, Bld#2. 5. All work in the right of way needs to be cordinated with Paul Rosenboom at 791-3154 ext 234. No further comments. 6/29/07 |
07/05/2007 | ASHOFFS1 | PIA COORDINATOR | CUSTOMER CALLED | Completed | PLEASE DELIVER RESUBMITTALS TO ANGIE IN DEVELOPMENT SERVICES FOR PROCESSING. |
07/05/2007 | ASHOFFS1 | PIA COORDINATOR | OUT TO CUSTOMER | Completed | PLEASE DELIVER RESUBMITTALS TO ANGIE IN DEVELOPMENT SERVICES FOR PROCESSING. |