Permit Number: T07OT02454
Parcel: 140292080

Review Status: Completed

Review Details: RESUBMITTAL - SITE ALL

Permit Number - T07OT02454
Review Name: RESUBMITTAL - SITE ALL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
02/13/2008 DAVE MANN FIRE REVIEW Approved
02/15/2008 ANDREW CONNOR NPPO REVIEW Approved
02/15/2008 ANDREW CONNOR LANDSCAPE REVIEW Denied 1. An unpaved planting area, which is a minimum of thirty-four (34) square feet in area and four (4) feet in width, must be provided for each canopy tree. The measurement is always within the planter area and does not include any material which defines the outer edge of the unpaved area per DS 2-06.3.3.C. Revise Detail #6 on Sheet SP-1 to meet requirement.

2. The site plan and landscape plan must show identical site layout to avoid conflict between the two plans. Ensure that all changes to the site plan are reflected on the landscape plan.
02/15/2008 ANDREW CONNOR ZONING REVIEW Denied Heather Thrall, zoning March 5, 2008

Per last review:

1) new class 2 bike parking must be within 50' of building entry. Per my scale, it's over that, based upon the noted entry.

2) Your detail that you reference for bike parking, detail 4 - is entirely missing on sheet SP.1. Please provide the detail and please reference DS 2-09 on the internet for acceptable bike parking figures.

3) Per PAAL connections from new parking to old parking at a width of less than 24' noted, I acknowledge your response that I was previously measuring to the lip of a gutter. Either label as lip of gutter or provide detail - the drawing appears to show that the PAALs are less than 24 if they are not labeled appropriately.

4) The 2000 city approved site plan clearly shows a required sidewalk that is leading to the existing parking lot north of the building. If its not there in real conditions, provide a note stating the sidewalk will be installed and provide the width and a slope note.

Heather.Thrall@tucsonaz.gov
02/19/2008 JASON GREEN ENGINEERING REVIEW Approved DATE: February 19, 2008
SUBJECT: 3535 E Valencia Road- 3rd Engineering Review New Parking Lot Expansion
TO: Metro Permits Express Attn: Lisa Bowers
LOCATION: T15S R14E Sec09 Ward 5
REVIEWERS: Jason Green, CFM
ACTIVITY: T07OT02454 (Site Plan) and T07BU02273 (Grading Plan)


SUMMARY: Engineering Division of Development Services Department has received and reviewed the revised site plan (T07OT02454), grading plan (T07BU02273), Drainage Report (O'Neill Engineering, 26OCT07, revised 21DEC07), Stormwater Pollution Prevention Plan (O'Neill Engineering, 30OCT07, revised 21DEC07), and Geotechnical Engineering Evaluation (Pattison-Evanoff Engineering, LLC, 18DEC07) for the above referenced property. Engineering Division recommends approval of the site plan, grading plan and Stormwater Pollution Prevention Plan (SWPPP) at this time.

§ Call for a Pre-construction meeting prior to start of earthwork. To schedule a DSD Pre-construction meeting, SWPPP inspection or general Engineering Inspections, call IVR (740-6970), or schedule with a Customer Service Representative at the Development Services Department, or contact DSD Engineering at 791-5550 extension 2101, or schedule inspections online at:

http://www.ci.tucson.az.us/dsd/Online_Services/Online_Permits/online_permits.html

§ Review and approval from TDOT Permits and Codes for all improvements within the public right-of-way will be required. A right-of-way use permit application will be required prior to construction. Refer to the following links for TDOT Forms and applications:

a) http://www.tucsonaz.gov/dsd/Forms_Fees___Maps/Applications/applications.html /
b) http://www.dot.ci.tucson.az.us/engineering/pia.php
c) Or contact Thad Harvison at 837-6592 for all additional questions regarding r-o-w.


If you have any questions I can be reached at 837-4929.



Jason Green, CFM
Senior Engineer Associate
Engineering Division
Development Services
03/05/2008 HEATHER THRALL ZONING HC SITE REVIEW Denied see zoning comments
03/12/2008 DROBEY1 PLUMBING-COMMERCIAL REVIEW Needs Review

Final Status

Task End Date Reviewer's Name Type of Review Description
03/12/2008 DELMA ROBEY APPROVAL SHELF Completed
03/12/2008 DELMA ROBEY OUT TO CUSTOMER Completed
03/12/2008 DELMA ROBEY REJECT SHELF Completed