Permit Number: T07CM04780
Parcel: 12009308A

Address:
4823 S 6TH AV

Review Status: Completed

Review Details: RESUBMITTAL

Permit Number - T07CM04780
Review Name: RESUBMITTAL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
01/22/2008 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Denied Comment not addressed. Reprint M1.1 so that the background is legible. Reference Section 106.3.1, IMC 2006.
01/22/2008 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Denied 1. Comment not addressed. Include all fixtures when calculating the total demand and determining pipe sizes (i.e. correct the arithmetic in the calculations). Reference Section 610.1, UPC 2006.
2. Comment not addressed. Calculate the water demand using the fixture units shown in Tables 6-5 or A-2 (use assembly fixture units for the water closets). Reference Section 610.3, UPC 2006.
3. Comment not addressed. Provide the rim elevation of the sanitary manhole and the first floor elevation. Determine the need for a backwater valve per Section 710.1, UPC 2006, as amended by the City of Tucson.
4. Comment not addressed. Show the size, material, and slope of the new building sewer (sheet G0.2). Reference Sections 103.2.3 and 718.1, UPC 2006.
5. Comment not addressed. Provide cleanouts in the building sewer at intervals not exceeding 100 feet and show how they are to be installed. Reference Sections 719.1 and 719.5, UPC 2006.
01/28/2008 LINDA BUCZYNSKI ELECTRICAL-COMMERCIAL REVIEW Denied TRANSMIT ORIGINAL DRAWINGS WITH NEXT SUBMITTAL.

PLEASE CALL AT 791-5550 X1106 OR EMAIL AT Linda.Buczynski@tucsonaz.gov
IF YOU CARE TO DISCUSS.

1. Provide electrical power for EF-3. Reference Sheet M1.1.
2. Provide electrical power for WH-1 and WH-2. Reference Sheet P2.1.
3. Short circuit calculation, with a utility available fault current of 22,000A for this 400A commercial single-phase service, is based upon an underground secondary of at least 45' in length. The underground secondary on the plans scales out to be about 15'.
4. Short circuit calculation uses a 145' utility secondary length. The underground secondary on the plans scales out to be about 15'.
5. Short circuit calculation assumes AFC to be at the utility transformer. Per TEP SR-510 single phase available fault currents are given at the line terminals of the metering equipment.
6. It appears that this submittal is the same as the drawings reviewed 12/21/07.
01/28/2008 BIANCA RAMIREZ ENGINEERING REVIEW Approved
02/05/2008 SREEVES1 ZONING REVIEW Needs Review
02/05/2008 WILLDAN ADA REVIEW Needs Review
02/05/2008 WILDAN 2ND PARTY REVIEW REVIEW Needs Review

Final Status

Task End Date Reviewer's Name Type of Review Description
02/05/2008 SUE REEVES OUT TO CUSTOMER Completed