Permit Review Detail
Review Status: Completed
Review Details: REVISION - - 8TH
Permit Number - T07CM04510
Review Name: REVISION - - 8TH
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 12/08/2014 | DAVID RIVERA | ZONING | REVIEW | Reqs Change | Project: T07CM04510 (additions) From: David Rivera, Principal Planner Address: 702 W Irvington Road TRANSMITTAL DATE: Decmber 8, 2014 DUE DATE: December 15, 2014 Additions annd change of use. 01. Zoning has reviewed the building plans but cannot do a compparison to the proposed revisions to the DP until the DP has gone through at least one review. 02. Zoning will do a full review of the building plans on the next submittal and do a comparison with the DP as it pertains to the zoning purview. The DP must be completely approved before zoning will approve the building plans. |
| 12/08/2014 | ERIC NEWCOMB | BUILDING-COMMERCIAL | REVIEW | Reqs Change | 1. SHEET S-3.1; ROOF FRAMING PLAN: WHAT HAPPENED TO THE WOOD LINTEL SCHEDULE THAT WAS INCLUDED IN THE APPROVED SET? NOW THE WOOD LINTELS ARE INDICATED AS 'WLX' ON THE PLAN. 2. SHEET S-5.2; DETAIL 228: PROVIDE THE SLOPE OF THE PIPE BRACE, OR THE ELEVATION AT WHICH IT ATTACHES TO THE COLUMN. 3. STRUCTURAL CALCULATIONS (SHEET 50); SHEET S-2.1 FOUNDATION PLAN): THE SHEARWALL IN THE CALCULATIONS IN THE NORTHEAST CORNER ON GRID CA DOES NOT SHOW UP ON SHEET S-2.1. CLARIFY. 4. GENERAL: PROVIDE WRITTEN RESPONSES TO ALL REVIEW COMMENTS. |
| 12/10/2014 | LOREN MAKUS | ENGINEERING | REVIEW | Approved | |
| 12/11/2014 | MARTIN BROWN | FIRE | REVIEW | Approved | |
| 12/16/2014 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Reqs Change | 1. Demonstrate energy code compliance for the addition to the building envelope using calculations based on the current code. Provide sufficient detail on the drawings to evaluate the energy compliance of the building envelope. The information shall, as a minimum, include U-factors of the envelope systems and fenestration components, along with the R-values of the insulation and the SHGC for the fenestration. Reference: Sections C101.4.3, C101.5, C103.2 and C401.2, International Energy Conservation Code 2012. 2. Provide NFRC fenestration product ratings for the U-factor and the SHGC values on COMcheck or use the appropriate default U-factor and SHGC values from Tables C303.1.3 (1), C303.1.3 (2) and C303.1.3.(3), IECC 2012. Reference: Section C303.1.3, IECC 2012. 3. Show how the "Additional Efficiency Package Requirements" noted in Section C406, IECC 2012 is to be addressed. Reference: Section C401.2.1, IECC 2012. 4. Show that the mechanical systems for the building addition comply with the current energy code; e.g. provide the COMcheck Mechanical Compliance Certificate. 5. Provide heating and cooling load calculations that justify the capacities of the heating and cooling equipment specified for the project. Reference: Sections C403.2.1 and C403.2.2, IECC 2012. |
| 12/16/2014 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Reqs Change | Provide roof drainage and hydraulic scupper size calculations based on the 100-year hourly rainfall rate for Tucson, 3" per hour. Provide overflow protection for the roof. Reference: Sections 1106.1, 1106.4, and 1108.3, IPC 2012. |
| 12/19/2014 | KEN VAN KARSEN | ELECTRICAL-COMMERCIAL | REVIEW | Reqs Change | T07CM04510 1. 2012 IECC (interior) lighting calculation: provide ComCheck report, or Table C405.5.2(1) building area or (2) space-by-space for budget determination. 2. City of Tucson Outdoor Lighting Code (Ord #10963) compliance: notate that the rated color temperature of relocated fixtures shall not exceed 3500K, Section 402. Ken Van Karsen Electrical Plan Review PDSD, City of Tucson 520-837-4906 Kenneth.VanKarsen@tucsonaz.gov |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 12/22/2014 | AROMERO4 | APPROVAL SHELF | Completed |
| 12/22/2014 | AROMERO4 | OUT TO CUSTOMER | Completed |