Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Number: T07CM04358
Parcel: 13316033F

Review Status: Completed

Review Details: COMMERCIAL TI

Permit Number - T07CM04358
Review Name: COMMERCIAL TI
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
11/13/2007 HEATHER THRALL ZONING REVIEW Approved
11/13/2007 LOREN MAKUS ENGINEERING REVIEW Approved
11/14/2007 LINDA BUCZYNSKI ELECTRICAL-COMMERCIAL REVIEW Denied T07CM04358 11/14/07

1. It appears that the only new electrical load on the Floor Plan is the receptacle on K1-20, but this is not clear from the printout. Please clarify this, and produce panel schedules and load calculations as necessary.
2. In all cases where existing feeders are being replaced by new feeders, and where it is necessary to round up to meet overcurrent protection requirements at the conductor's ampacity, either provide the electrical load for the panel, or document pre-existing conditions.
3. City does not allow fault current-limiting characteristics of overcurrent protective devices to attentate AFC at panelboards. For the new panelboard, please provide fault calculations.
11/14/2007 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Passed
11/14/2007 RONALD BROWN BUILDING-COMMERCIAL REVIEW Denied 1. provide building dimensions to property line
2. define more clearer, the extent of slab replacement and reference slab connection details
3. define rbar o.c. at detail 4/A2.0
11/14/2007 ROBERT SHERRY WATER REVIEW Approved
11/14/2007 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Denied 1. Provide water supply isometrics. Reference Section 103.2.3, UPC 2006.
2. Provide waste and vent isometrics. Reference Section 103.2.3, UPC 2006.
3. Provide material standards for all plumbing fixtures being provided by others. Reference Section 401.1, UPC 2006.
4. Is a shut off valve existing for the building service entrance? Reference Section 605.2, UPC 2006.
5. Clarify keynote #11 on sheet P1.1. Reference Section 103.2.3, UPC 2006.
6. Provide roof drainage calculations for the project area. Provide sizing information for the roof scupper. Provide overflow protection for the roof. Reference Section 1106.0, UPC 2006.
7. Provide the total connected load for the gas meter, the longest developed length for the piping system and the size of the new pipe. Reference Section 1209.1, UPC 2006.
11/27/2007 CAGUILA1 WWM REVIEW Needs Review
11/27/2007 CAGUILA1 FIRE REVIEW Needs Review
11/27/2007 BETH GRANT COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Needs Review