Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL - SITE ALL
Permit Number - T07CM03499
Review Name: RESUBMITTAL - SITE ALL
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 05/12/2009 | RONALD BROWN | ZONING HC SITE | REVIEW | Approved | |
| 05/13/2009 | DAVE MANN | FIRE | REVIEW | Denied | Portions of the home have greater than 150 hose lay from street. Move the building closer to the road or provide automatic fire sprinklers. |
| 05/21/2009 | ANDREW CONNOR | LANDSCAPE | REVIEW | Denied | 1. The Regulated Area for watercourses is defined under this Development Standard 9-06.2.2. B.2 & 3. Development shall not extend beyond the banks of a watercourse and the area within 50 feet of the top of the bank. Revise plans as necessary to comply with Development Standard. 2. Ensure that all Engineering and Zoning comments and concerns are addressed and appropriate revisions are made to site, grading and NPPO plan. |
| 05/21/2009 | MATT FLICK | ENGINEERING | REVIEW | Denied | Sheet A.1 - The FEMA flood zone is "AH", not "X". Exhibit L.1 - The finished floor elevation (ffe) must be a minimum of 1' above the FEMA-determined water surface elevation at the upstream point of the structure. Please correct the ffe. It is suggested that the fill pad be elevated above the FEMA-determined water surface elevation at the upstream point of the fill pad. Doing so may facilitate removal of the structure from the FEMA floodplain and reduce the need to protect the top of the fill pad from erosion by the floodwaters. Exhibit L.2 - The finished floor elevation (ffe) must be a minimum of 1' above the FEMA-determined water surface elevation at the upstream point of the structure. Please correct the ffe. It is suggested that the fill pad be elevated above the FEMA-determined water surface elevation at the upstream point of the fill pad. Doing so may facilitate removal of the structure from the FEMA floodplain and reduce the need to protect the top of the fill pad from erosion by the floodwaters. Exhibit L.2 - Placing of a fill pad in a FEMA floodplain requires sufficient armoring (riprap, vegetation, etc.) to resist erosion. If the fill extends less than 25' from the building edges, certification is required by a P.E. that the armoring is sufficient (this can be done on the Elevation Certificate or other format). |
| 05/22/2009 | ANDREW CONNOR | NPPO | REVIEW | Passed | |
| 06/03/2009 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | Comment not addressed. Provide the rim elevation of the next upstream sanitary manhole. Determine the need for a backwater valve per Section 710.1, UPC 2006, as amended by the City of Tucson. |
| 06/08/2009 | MICHAEL ST. PAUL | ZONING | REVIEW | Denied | CDRC TRANSMITTAL FROM: Michael St.Paul, Planning Technician PROJECT: T07CM03499 (T07BU01779 Grad & T07OT01938 FUP) 1461 South Camino Santiago New SFR TRANSMITTAL: June 8, 2009 COMMENTS: Please attach a response letter with the next submittal, which states how all Zoning Review Section comments regarding the Land Use Code and Development Standards were addressed. 1) This review is for a proposed single-family residence (SFR) in the R-1 Zone (LUC Section 2.3.4.2.A.1). The Development Designator is "G" (LUC Section 3.2.3.1.B) and the Perimeter Yard Indicator is AA (LUC Section 3.2.6.4). 2) Provide both a floor plan and dimensioned elevation drawings (LUC Section 3.5.7.E, .F, .G & .H). 3) Provide the wall heights on the plot plan. Go to LUC Section 3.2.6.3 for the correct methods of measurement for setbacks. 4) Clearly dimension the location of all structures on the plot plan from nearest edge of SFR to each lot line. Use the plot plan model and instruction we hand out at the counter. 5) A lot combination shall be required prior to approval of the plot plan. 6) There may be further comments relative to the information provided with next submittal. |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 06/15/2009 | SUE REEVES | APPROVAL SHELF | Completed |
| 06/15/2009 | CPIERCE1 | OUT TO CUSTOMER | Completed |