Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Number: T07CM03497
Parcel: 14029212B

Review Status: Completed

Review Details: COMMERCIAL NEW

Permit Number - T07CM03497
Review Name: COMMERCIAL NEW
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
08/24/2007 DAVE MANN FIRE REVIEW Denied Please add the following automatic sprinkler criteria to the plans:

1. The hazard classification of the occupancy including any special hazards.
2. The design standard to be used.
3. The availability and adequacy of the water supply.
4. The design density and the area of operation.
08/30/2007 DAVID RIVERA ZONING REVIEW Denied 08/30/07

Development Services Department
Zoning Review Section

David Rivera
Principal Planner

Comments:

1. Zoning has reviewed the building plans but cannot approve them at this time until the plans have been completely approved through the commercial review process and complies with the CDRC approved and stamped development plan.

2. A site card with DSD approvals by Fire, Zoning, Handi-cap, Engineering, and Landscape/NPPO including the approved development plan stamped for site plan approval and signatures is required before the grading plan can be approved by Zoning. Two copies of the CDRC approved tentative plat/development plan, landscape and NPPO plans are to be submitted with the grading plan packet for processing and approval as a site plan. No fees are involved in re-stamping the development/tentative plat plans as an approved site plan. The tentative plat/development plan may be walked through for stamps and site card sign off. Submit the following: two copies of the stamped development plan, landscape and NPPO plans must be included with the grading plans packet processed together for site approval.

3. Zoning will re-review and approve the building plans on the next submittal providing the requested plans are included with the building plan package and the building structural portions of the plan review have been approved. See comment 2 for additional info regarding the site plan process.

4. As of this review date the Development plan (D07-0006) under the CDRC review process has not been approved.
09/06/2007 JOHN WILLIAMS COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Completed Impact Fee's Do Apply; West District; 20,032 Square Feet of Educational Use (Office); $47,365.58
09/14/2007 SREEVES1 2ND PARTY REVIEW REVIEW Denied September 13, 2007 CITY OF TUCSON - FIRST CHECK
Tucson Appl. No. T07CM03497
Bureau Veritas Job No. 01007-161001.071

Jim Hedgepath
3428 E. Indian School Rd.
Phoenix AZ 85018

Re: Plan Review: Tutor Time
Address: 3690 E. Hemisphere Loop


Dear Mr. Hedgepeth


Bureau Veritas North America has completed a First review of the following documents on behalf of the City of Tucson:

Plans: One (1) set of building plans ( 78 Sheets, CS through SS-1) Sealed by David M. Cardanas, Registered Architect. Dated August 21, 2007.

Structural Calculations: One (1) Set.

Soils Report: One (1) report.


These documents were reviewed only for their conformance to the provisions of the 2006 International Building Codes (i.e., State of Arizona and Tucson amended 2006 IRC, 2006 IMC, 2005 NEC and 2006 IPC).

Please submit an itemized response letter and required number of complete and revised documents with all revisions clouded.


Sincerely,

Bureau Veritas North America




Shelley Knuffke
ICC Plans Examiner









SKK;skk




A. The following plan review comments are based on the City of Tucson Building Regulations and referred to the 2006 International Building Code.

B. Please respond in writing to each comment by marking the attached comment list or creating a response letter. Indicate which detail, specification, or calculation shows the requested information. Your complete and clear responses will expedite the re-check and hopefully, approval of this project. Thank you for your assistance.

C. These plan review comments are based on building code items only. If site-related comments are applicable to this project, they will be generated by others (e.g., County Engineering, Public Works, Health, etc.).




GENERAL REQUIREMENTS:

The City of Tucson adopted the 2006 Building Codes. July 1, 2007. All plans must comply with the current code. Sheet CS states the use of the 2003 IBC. Please make any changes necessary to comply with the current code and resubmit the plans.

2. Please delete all references and details that are not to be used for this project.





If you have any questions regarding the above comments, please contact Shelley Knuffke at (520) 576-8400 between 8:00 A.M. to 5:00 P.M., M-F.
09/17/2007 ROBERT SHERRY WATER REVIEW Denied 1. Show the location of the required reduced pressure backflow assembly downstream of the water meter on the drawings, specify the reduced pressure backflow assembly being installed, and indicate the size of the assembly. Reference COT Ordinance 9976, http://www.tucsonaz.gov/water/docs/backflow-ord.pdf
09/20/2007 GERRY KOZIOL WWM REVIEW Denied needs manhole tap permit
09/21/2007 JASON GREEN ENGINEERING REVIEW Denied Building plan can not be approved prior to site plan approval.

Final Status

Task End Date Reviewer's Name Type of Review Description
09/25/2007 CINDY AGUILAR OUT TO CUSTOMER Completed
09/25/2007 CINDY AGUILAR REJECT SHELF Completed