Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL
Permit Number - T07CM03057
Review Name: RESUBMITTAL
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
07/15/2008 | RONALD BROWN | BUILDING-COMMERCIAL | REVIEW | Approved | |
07/17/2008 | TERRY STEVENS | ZONING | REVIEW | Denied | 07/17/08 Development Services Department Zoning Review Section Terry Stevens Lead Planner Comments: 1. The building plan has been reviewed by Zoning Review Section but cannot approve the plan until it has been approved by the Engineering, and Landscape Review Sections and until all zoning comments or concerns have been addressed. 2. Zoning could not verify that the building plan was in compliance with the approved site plan. Please submit two copies of the approved and stamped site, landscape, and NPPO plans with the next building plan submittal. 3. Zoning will re-review the building plan on the next submittal to insure compliance with the approved site plan. Additional comments may be forthcoming. |
07/23/2008 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | 1. Detail F/A301 shows an overflow capability for the collector box if the downspout is blocked but no overflow capability for the roof scupper. Provide secondary (overflow) drainage for the main roof (i.e. if the roof scupper is blocked). Reference: Section 1101.11.2, UPC 2003. 2. Sheet P101 has been printed with the background too faint to be seen. Please reprint this sheet. Reference: Section 103.2.3, UPC 2003. |
07/24/2008 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | 1. Comment not addressed. The value "Ez" for ceiling supply/ceiling return using gas heat is 0.8, not 1.0. Reference: Table 6-2, ASHRAE Standard 62.1-2004. 2. To determine the required amount of outside air for a system that uses a single air handler to supply outside air and recirculated air to more than one zone, Section 6.2.5, ASHRAE Standard 62.1-2004, shall be used. Reference: Section 403.3, IMC 2006, as adopted by the City of Tucson. |
08/06/2008 | LOREN MAKUS | ENGINEERING | REVIEW | Denied | The site plan must be approved before the building plan can be approved. |