Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL TI
Permit Number - T07CM02804
Review Name: COMMERCIAL TI
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 07/02/2007 | JOHN WILLIAMS | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Passed | |
| 07/03/2007 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | 1. Show that a separation of at least ten feet exists between air intake openings and exhaust openings. Reference 401.5, IMC 2003. 2. Provide information on the sequence of operation for the restroom exhaust ("wall switch time clock"?) to show that recirculation of the air from the restroom will not occur. Reference Section 403.2.1, IMC 2003. 3. Show how adequate access is being provided for the equipment located on the roof (the architectural drawings indicate the presence of a roof hatch but no ladder). Reference Section 306.5, IMC 2003. |
| 07/03/2007 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | 1. Show the route and termination of the T&P relief pipe for the water heater. 2. Provide details of the water heater support (i.e. it is not shown on the architectural drawings). 3. Provide a drinking fountain. |
| 07/03/2007 | ROBERT SHERRY | WATER | REVIEW | Approved | |
| 07/03/2007 | CHRIS KIEL (WILDAN) | BUILDING-COMMERCIAL | REVIEW | Denied | 1) Please provide a drinking fountain in accordance with table 2902.1 of the 2003 IBC. 2) Please provide verification that the window adjacent to the conference room door complies with section 2406 of the 2003 IBC. 3) Please provide structural verification that the existing structural components can support the loads associated with the new mechanical units per section 106.1.1 of the 2003 IBC. 4) Please provide sheet A2 as referenced throughout the plans per section 106.1.1 of the 2003 IBC in order to verify compliance with chapters 10, 11, and 12 of the 2003 IBC and ANSI 117.1-2003. 5) Please provide details/sections for the support of the water heater over room 115 per section 106.1.1 of the 2003 IBC. 6) Please provide a COMcheck for the mechanical installations in order to verify compliance with the 2003 IECC. A free downloadable copy of COMcheck is available at www.energycodes.gov. |
| 07/12/2007 | DROBEY1 | WWM | REVIEW | Needs Review | |
| 07/12/2007 | DROBEY1 | ELECTRICAL-COMMERCIAL | REVIEW | Needs Review | |
| 07/12/2007 | DROBEY1 | ENGINEERING | REVIEW | Needs Review | |
| 07/12/2007 | DROBEY1 | ZONING | REVIEW | Needs Review | |
| 07/12/2007 | DROBEY1 | FIRE | REVIEW | Needs Review |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 07/12/2007 | DELMA ROBEY | APPROVAL SHELF | Completed |
| 07/12/2007 | DELMA ROBEY | OUT TO CUSTOMER | Completed |
| 07/12/2007 | DELMA ROBEY | REJECT SHELF | Completed |