Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Number: T07CM02513
Parcel: 14117007D

Review Status: Completed

Review Details: POST 3RD PARTY REVIEW

Permit Number - T07CM02513
Review Name: POST 3RD PARTY REVIEW
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
07/09/2007 JOHN WILLIAMS COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Passed
07/11/2007 MARTIN BROWN FIRE REVIEW Approved
07/12/2007 Michael Wyneken ZONING-CITY HALL REVIEW Denied 1) Enlarged dimentional plan dimentions do not match dimentions in antenna detail. Max. stand-off per SE conditions is one foot six inches.

2) Add note stating the new facilities will be painted the same color as existing.

3) Add note: wire ports shall be no higher or lower than the antenna panels. Cables shall be routed through the interior of the pole, and shall not be visible.
07/13/2007 TERRY STEVENS ZONING REVIEW Denied CDRC TRANSMITTAL

TO: Development Services Department
Plans Coordination Office

FROM: Terry Stevens
Lead Planner

PROJECT: T07CM02513
7555 S. Houghton Rd.
Add Antennas to Existing Tower

TRANSMITTAL: 07/13/07

COMMENTS: Please resubmit revised drawings along with redlines and a response letter, which states how all Zoning Review Section comments regarding the Land Use Code and Development Standards were addressed.

1. Revise the project address indicated on all plans to the correct address.

2. The indicated adjacent zoning to the east of the proposed site, (Zoning: P), is incorrect. The correct zoning is R-1. Revise.

3. The Cell Tower site plan has been reviewed by Zoning Review Section but cannot approve the plan until it has been approved by the Special Exception section of DSD.

4. A copy of the Special Exception approval letter must accompany the plan. Additional comments may be forth coming based on approval conditions.

5. Provide a copy of the last approved site plan for the self-storage site.

6. On the site plan clearly indicate the location of the required technician parking space.

7. It appears the electrical service is being located on a different parcel than the cell tower site. An electrical easement will be required from the panels to the parcel

8. An access easement is required to be provided to the two parcels from Valencia. Parcels cannot be land locked. Provide recording docket and page information on the site plan for the access easement to the cell tower parcels. Clearly indicate the limits of the access easement.

If you have any questions about this transmittal, please call Terry Stevens, (520) 837-4961
07/25/2007 JAY HOGAN OPERATIONS REVIEW Approved

Final Status

Task End Date Reviewer's Name Type of Review Description
08/28/2007 VFLORES1 OUT TO CUSTOMER Completed