Permit Number: T07CM02348
Parcel: 115180050

Review Status: Completed

Review Details: COMMERCIAL TI

Permit Number - T07CM02348
Review Name: COMMERCIAL TI
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
06/08/2007 JOHN WILLIAMS COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Passed
06/11/2007 ROBERT SHERRY WATER REVIEW Approved
06/11/2007 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Denied 1. Clarify the proposed scope of work. Sheets D1 and A1 appear to indicate the addition of a urinal in room 166 and additional lavatories in rooms 107, 114 and 115. Reference Section 103.2.3, UPC 2003.
2. Show how the new water piping relates to the existing water supply system and show that the additional connections do not cause the existing piping to be overloaded. Reference Section 101.5.1, UPC 2003.
3. Appliances (e.g. ovens, ice makers, espresso machines, etc) to be directly connected to the water supply system that do not have listed, integral backflow preventers or integral air gaps conforming to Table 6-3, UPC 2003 require backflow prevention. Reference Sections 602.3, 603.0, and Table 6-2, UPC 2003.
4. Provide specifications for the appliances provided by the owner (e.g. the post-mix section, the icemaker). Reference Section 103.2.3, UPC 2003.
5. The plumbing fixture schedule calls out a Sloan Royal model 136-1 for the urinal, P-3. That model valve is for a water closet and uses at least 1.6 GPF. Reference Section 402.1, UPC 2003, as amended by the State of Arizona. (ARS Title 45, Chapter 1, Article 12)
06/11/2007 DAVE MANN FIRE REVIEW Approved
06/11/2007 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Denied 1. Specify the minimum resistance (R-value) of the duct insulation to be used on this project. Reference Section 803.2.8, IECC 2003.
2. Show how the hangers for the new fan coil units are being attached to the building structure and verify that the existing structure is capable of supporting the additional dead load. Reference Section 302.1, IMC 2003.
3. Show how the heat pump units are to be installed. Reference Sections 304.9 and 306.1, IMC 2003.
4. Provide auxiliary drain pans or secondary drain systems for fan coil units. Reference Section 307.2.3 IMC 2003.
5. Provide calculations demonstrating adequate ventilation. Reference Section 401.2, IMC 2003.
6. Provide an approved commercial kitchen hood over all commercial cooking or heat-producing appliances. Reference Sections 507.1 and 507.2, IMC 2003.
06/14/2007 PATRICIA GILBERT ENGINEERING REVIEW Approved NON-SUBSTANTIAL IMPROVEMENT



Date: June 27, 2007

Address: 1601 North Oracle Road

Permit Numbers: T07OT00938

Floodplain type: AE

Description of Work: Tenant Improvement





Type permit: Non-residential

Year of construction of existing structure: 1961

Value of work: $ 323,653

Prior permit activity value $ 0

Value of structure: $ 767,047 based on $34.26 per square foot

Increase in Flood Damage Potential: % 42
07/02/2007 LEERAY HANLY BUILDING-COMMERCIAL REVIEW Denied 1) Provide break down of how accessibility is being addressed. Detail application of section 3409.6 of the 2003 IBC.

2) Provide details for installation of new ceilings, soffits, partition bracing, infill areas, etc.

3) The modifications to corridor 120 have cut off access to the proposed accessible restrooms on that corridor. How is equal accessibility going to be accomplished for multiple meeting rooms?

4) Please address accessibility at bar per section 904 of the 2003 ANSI 117.1.

5) New roof sheathing and rafter repairs need to be addressed in details and valuation of job.

6) Please clarify if hard lids noted on pp A3 are existing or provide details for construction. Please clarify areas of new ceiling grids on pp A3.

7) Provide site plan indicating accessible route from public way into building.

8) Exit signs will be required per section 1011 of the 2003 IBC. Please indicate exits out of lobby area, lounge and internet cafe.
07/03/2007 LINDA BUCZYNSKI ELECTRICAL-COMMERCIAL REVIEW Denied TRANSMIT ORIGINAL DRAWINGS WITH NEXT SUBMITTAL.
PLEASE CALL AT 791-5550 X1106 OR EMAIL AT Linda.Buczynski@tucsonaz.gov
IF YOU CARE TO DISCUSS.

1. It appears that the totals for Phases A, B, and C on Panel M are 32955, 30815, and 30395 VA, respectively, not 27655, 26585, and 26645. This effects the final amperage on the panel, and hence the amount of spare capacity. Also, it is not clear that the outdoor fan units with the HPs were added to the loads. For more corrected totals, please note that Phase C of Panel M1 is 4650, not 4290 (the receptacle load on Ckt 23 was overlooked). And Ckt 16 on Panel B1 appears to have 1596 VA, not 504, which carries through to the total on Phase B on that Panel and on Panel M.
2. Each conduit comprising the feeder to Panel M shall have a #3, minimum, GND.
3. Please eliminate the redundant GND on the line side of Panel M.
4. Show the location of Panel A1 on the plans. Note that there is a Panel A on the plans, without panel schedule.
5. Since Panel EB is to be new, show its panel schedule and electrical loads.
6. Lighting does not correspond to that indicated on the Reflected Ceiling Plan. Reference Sheet A3.
7. Electrical Power and Lighting indicate that the work for the Einstein Bagelry are to be done by others, on a separate permit. However, a set of unsealed drawings for the bagelry are included in this submittal. No indication that these plans are just for reference. Please clarify.
8. It appears that the Load Calculations only reflect the new loads. Provide service load calculations, total.
9. Please note that the following question has been forwarded to TEP: "A set of plans at 1601 N Oracle Road, Building 9, is currently under review. The Engineer is citing 75,100A of Available Fault Current for a 2000A, 208V service originating at a bank of pole-mounted TEP transformers. This appears abberant, because SR-510 does not list a value for Available Fault Current at a 2000A service from a pole-mounted transformer. And the value published for a 1600A, 208V service from a pole-mounted transformer 77,400A, clearly larger than 75,100.
Should I have the Engineer revisit his values, or is this site somehow unique?"
07/09/2007 GERRY KOZIOL WWM REVIEW Approved