Permit Number: T07CM02343
Parcel: 11105026D

Review Status: Completed

Review Details: OTHER

Permit Number - T07CM02343
Review Name: OTHER
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
07/23/2007 CHRIS KIEL (WILDAN) BUILDING-COMMERCIAL REVIEW Denied 1) Please provide structural calculations for the entire addition in accordance with section 106.1.1 of the 2003 IBC. In addition, please provide verification from the manufacturer that the specified I-joist can cantilever the specified distances. If the joists are to be a deferred submittal, please state so on the plans and provide a letter signed by the building official denoting the deferred items. If not, specify the required blocking and hardware associated with the roof framing.

2) Please provide general structural information regarding the type of building components to be installed per section 106.1.1 of the 2003 IBC (i.e. assumed soil conditions, strength of the concrete to be used, grout strength, etc.).

3) Please coordinate the plans, details, and sections throughout the submittal per section 106.1.1 of the 2003 IBC (i.e. structural foundation and framing plan section with the location of the sections, locations for most of the structural details with the associated plans, planter soil depth between the details, sections and elevations, continuation of bearing wall through to the screen wall between elevations, plans, sections and details, etc.). Revise accordingly.

4) Please specify the listing for the 2-coat stucco system per section 106.1.1 of the 2003 IBC.

5) Please provide verification that an accessible route exists from the patio area to the public way per chapter 10 of the 2003 IBC.
07/23/2007 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Denied 1. Provide calculations to show that the water supply line will be protected from freezing.
2. Clarify how the water supply is to be connected to the existing water pipe.
3. Show how the blowdown and drainage of the evaporative cooler is to be accommodated.
07/23/2007 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Denied 1. Provide specifications for the proposed evaporative cooler, including the manufacturer, model number, and the operating weight.
2. Clarify the diffuser to be used.
09/24/2007 DROBEY1 ELECTRICAL-COMMERCIAL REVIEW Needs Review