Permit Number: T07CM01424
Parcel: 11308011A

Address:
3148 N 1ST AV

Review Status: Completed

Review Details: REVISION - - 3RD

Permit Number - T07CM01424
Review Name: REVISION - - 3RD
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
04/10/2008 LINDA BUCZYNSKI ELECTRICAL-COMMERCIAL REVIEW Approved T07CM01424 4/8/08

1. Provide the electrical load on the panel schedule for Ckt P1-6.
2. Phase C on Panel P1 is overloaded even before the application of demand factors for largest motor and continuous load.
3. Add the ACs to load service load calculations.
4. Provide load calculations for both service 100A disconnect switches.
5. Please add the following note to the fault calculations: "Contractor shall provide TEP available fault current." Reference TEP SR-510.