Permit Number: T07CM01074
Parcel: 11901065B

Address:
3301 S 6TH AV

Review Status: Completed

Review Details: POST 3RD PARTY REVIEW

Permit Number - T07CM01074
Review Name: POST 3RD PARTY REVIEW
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
02/04/2008 JOHN WILLIAMS COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Completed Impact Fee's Do Apply; West District; 4,400 Square Feet @ Retail; $17,544.40
02/04/2008 ROBERT SHERRY WATER REVIEW Approved
02/04/2008 DAVE MANN FIRE REVIEW Denied The types of construction shown on this plan conflict with the canopy drawings. A separate permit is required for the fuel systems.

Please include the following design criteria to the plans.
1. Flow data (static pressure, residual pressure, GPM)
Available from the Fire Department (520) 791-3234
2. The standard to be used in development of sprinkler system. (NFPA 13, NFPA 13R, or NFPA 13D)
3. The hazard classification of the building, including any special hazards.
4. The density required of the water supply.
02/05/2008 GERRY KOZIOL WWM REVIEW Denied 1: circle K - issued with grease interceptor
2: needs wastewater 5th floor credit evaluation if applicable
3: needs wastewater 5th floor review of location/method of connection to public sewer (manhole construction permit) need waste review of private sewer extensions for future parcels, easements, jt use agreements, etc.
02/19/2008 STEVE SHIELDS ZONING REVIEW Denied DSD TRANSMITTAL

FROM: Steve Shields
Lead Planner

PROJECT: Circle "K" 6th & I10
T07CM01074
Building Plan (2nd Review)

TRANSMITTAL DATE: February 25, 2008

1. The building plan has been reviewed by Zoning Review Section but cannot approve the plan until it has been approved by the Engineering, and Landscape Review Sections and until all zoning comments or concerns have been addressed.

2. Zoning could not verify that the building plan was in compliance with the approved site plan. Please submit two copies of the approved and stamped site, landscape, and NPPO plans with the next building plan submittal.

3. Zoning will re-review the building plan on the next submittal to insure compliance with the approved and stamped site plan. Additional comments may be forthcoming.

If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 837-4956.

C:\planning\grading\t07cm01074.doc

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised site plan and additional requested documents
02/21/2008 JASON GREEN ENGINEERING REVIEW Denied Building can not be approved prior to Tentative Plat and Site Plan approval.

Final Status

Task End Date Reviewer's Name Type of Review Description
04/16/2008 DELMA ROBEY OUT TO CUSTOMER Completed
04/16/2008 SHANAE POWELL REJECT SHELF Completed