Permit Number: T07CM00784
Parcel: 12314126D

Address:
711 E LESTER ST

Review Status: Completed

Review Details: COMMERCIAL TI

Permit Number - T07CM00784
Review Name: COMMERCIAL TI
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
07/09/2007 CHRIS KIEL (WILDAN) BUILDING-COMMERCIAL REVIEW Denied 1) Please provide a drinking fountain in accordance with table 2902.1 of the 2003 IBC.

2) Please provide the approved appeal from the Building Official regarding the requried toilet facilities per section 106.1.1 of the 2003 IBC.

3) Please provide emergency power for the egress illumination at the exit discharge adjacent to the required exits per section 1006.3 of the 2003 IBC.
07/09/2007 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Denied 1. Provide additional outside air for HP-3 to accomodate the specified exhaust air flow rate.
2. Show that the existing roof is capable of supporting the new heat pumps.
3. Revise the font size to 1/8", all upper case.
07/09/2007 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Denied 1. Provide site drawing showing the size and route of the building water supply along with the location and size of the water meter. Reference Section 103.2.3, UPC 2003.
2. Provide site drawing showing the size, route, and slope of the building sewer. Reference Section 103.2.3, UPC 2003.
3. Provide the minimum plumbing facilities required by Table 2902.1, IBC 2003, for education occupancy.
4. Provide material standards for all plumbing fixtures being provided by others. Reference Section 401.1, UPC 2003.
5. Show how the temperature of the hot water supply to the public lavatories is controlled. Reference Section 414.1, UPC 2003 and Section 804.3, IECC 2003.
6. Provide structural calculations to show that the water heater is safely supported. Reference Sections 310.0 and 314.5, UPC 2003.
7. Provide protection of the trap seals for all floor drains subject to infrequent use. Reference Sections 1007.0 and 1007.1, UPC 2003, as amended by the City of Tucson.
07/09/2007 ROBERT SHERRY WATER REVIEW Approved
07/10/2007 MICHAEL ST. PAUL ZONING REVIEW Approved
07/10/2007 LINDA BUCZYNSKI ELECTRICAL-COMMERCIAL REVIEW Denied T07CM00784 7/10/07

1. HP-1 and HP-2 are 3-phase units according to the Packaged Rooftop Heat Pump Schedule Sheet M-1. Coordinate with Mechanical and clarify.
2. HP-1 and HP-2 are to have MOCP 60 according to the Packaged Rooftop Heat Pump Schedule Sheet M-1. CB trip is 80 on the electrical panel schedule. Coordinate with Mechanical and clarify.
3. HP-3 is to have MOCP 40 according to the Packaged Rooftop Heat Pump Schedule Sheet M-1. CB trip is 70 on the electrical panel schedule. Coordinate with Mechanical and clarify.
4. Revise the font size used on the drawings to a minimum of 1/8-inch (all upper case). Reference Section 302.3, Uniform Administrative Code, 1997.
5. Water Heater is to be on Ckt A-9,11 on Electrical Plan. This is on Ckt A-10,12 on the panel schedule. Please clarify.
6. Demonstrate compliance with the Tucson Lighting Code, http://www.tucsonaz.gov/dsd/Codes___Ordinances/Tucson_Lighting_Code.pdf.
7. Heat pumps take 208V Sheet M-3. Electrical Power is 240V. Coordinate with Mechanical and clarify.
8. Water Heater is 208V per Sheet P-1. Electrical Power is 240V. Coordinate with Plumbing and clarify.
9. Provide TEP Available Fault Current.
10. Provide fault calculations.
11. If existing service is overhead, please document such on the electrical plans. Otherwise, apply for an underground to overhead waiver.
07/11/2007 GBONILL1 WWM REVIEW Needs Review
07/11/2007 BETH GRANT COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Needs Review
07/11/2007 GBONILL1 ENGINEERING REVIEW Needs Review
07/11/2007 MARTIN BROWN FIRE REVIEW Approved