Permit Review Detail
Review Status: Completed
Review Details: POST 3RD PARTY REVIEW
Permit Number - T07CM00640
Review Name: POST 3RD PARTY REVIEW
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 10/17/2007 | BETH GRANT | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Needs Review | |
| 10/17/2007 | STEVE SHIELDS | ZONING | REVIEW | Denied | DSD TRANSMITTAL FROM: Steve Shields Lead Planner PROJECT: Cendot Construction T07CM00640 Building Plan (1st Review) TRANSMITTAL DATE: October 17, 2007 1. The building plan has been reviewed by Zoning Review Section but cannot approve the plan until it has been approved by the Engineering, and Landscape Review Sections and until all zoning comments or concerns have been addressed. 2. Zoning could not verify that the building plan was in compliance with the approved site plan. Please submit two copies of the approved and stamped site, landscape, and NPPO plans with the next building plan submittal. 3. Zoning will re-review the building plan on the next submittal to insure compliance with the approved and stamped site plan. Additional comments may be forthcoming. If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 837-4956 C:\planning\grading\t07cm00640.doc RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised site plan and additional requested documents |
| 10/17/2007 | VFLORES1 | WATER | REVIEW | Needs Review | |
| 10/17/2007 | VFLORES1 | WWM | REVIEW | Needs Review | |
| 10/17/2007 | VFLORES1 | ENGINEERING | REVIEW | Needs Review |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 10/17/2007 | VFLORES1 | OUT TO CUSTOMER | Completed |