Permit Number: T07BU00762
Parcel: 10511061Q

Address:
4413 N STONE AV

Review Status: Completed

Review Details: RESUBMITTAL - GRADING ALL

Permit Number - T07BU00762
Review Name: RESUBMITTAL - GRADING ALL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
07/03/2007 PATRICIA GILBERT ENGINEERING REVIEW Denied DATE: July 4, 2007
ACTIVITY NUMBER: T07BU00762
PROJECT NAME: Tucson Mall Oil Stop
PROJECT ADDRESS: 4413 North Stone Avenue
PROJECT REVIEWER: Patricia Gilbert

The following items must be revised or added to the grading plan. Please include a response letter with the next submittal that states how all comments have been addressed.

RESUBMITTAL REQUIRED: GRADING PLAN

1. Prior to the grading plan being approved two copies of the approved development plan, landscape and NPPO plans must be approved as site plan. A site application card (yellow card) with the CDRC approved development plan must be stamped with signatures for DSD site approval by the following reviewing sections; Fire, Zoning, Handi-cap, Engineering, Plumbing and Landscape/NPPO. The development plan may be walked through for approval and site card sign off. No fees are involved in re-stamping the development/tentative plat plans as an approved site plan.

2. Dimension the sidewalk on the north side of the building.
07/19/2007 MICHAEL ST. PAUL ZONING REVIEW Denied July 19, 2007

Development Services Department
Zoning Review Section

Michael St.Paul
Planning Technician

T07BU000762 Grading Plans for D06-0041
4413 North Stone Avenue
(Second submittal)

Comments:

1. The grading plan has been reviewed by Zoning Review Section but cannot approve the plan until it has been approved by the Engineering, and Landscape Review Sections and until all zoning comments or concerns have been addressed.

2. In addition, we could not verify that the grading plan was in compliance with the approved development plan for Zoning Review. Please submit two copies of the approved and stamped Development Plan/Site Plan, Landscape, and NPPO plans with the next grading plan submittal. Please be aware that the Development Plan must also go through the Site Plan process. This is a walk through process in which the stamped approved Development Plan is also approved as a Site Plan.

3. Zoning will re-review the grading plan on the next submittal to ensure compliance with the approved development plan. Additional comments may be forthcoming.
07/20/2007 ANDREW CONNOR NPPO REVIEW Denied Submit a copy of the approved development plan including landscape plan for reference.The grading application will be reviewed for compliance only when the approved documents are included in the submittal. Revise grading plans as necessary to comply with the approved development plan.

Final Status

Task End Date Reviewer's Name Type of Review Description
07/23/2007 CINDY AGUILAR OUT TO CUSTOMER Completed
07/23/2007 CINDY AGUILAR REJECT SHELF Completed