Permit Number: T07BU00156
Parcel: 14027042C

Address:
2622 E BILBY RD

Review Status: Completed

Review Details: RESUBMITTAL - GRADING

Permit Number - T07BU00156
Review Name: RESUBMITTAL - GRADING
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
09/14/2007 STEVE SHIELDS ZONING REVIEW Denied DSD TRANSMITTAL

FROM: Steve Shields
Lead Planner

PROJECT: Bilby Industrial
T07BU00156
Grading Plan (4th Review)

TRANSMITTAL DATE: September 14, 2007

1. The grading plan has been reviewed by Zoning Review Section but cannot approve the plan until it has been approved by the Engineering, and Landscape Review Sections and until all zoning comments or concerns have been addressed.

2. Zoning could not verify that the grading plan was in compliance with the approved site plan. Please submit two copies of the approved and stamped site, landscape, and NPPO plans with the next grading plan submittal.

3. Zoning will re-review the grading plan on the next submittal to insure compliance with the approved and stamped site plan. Additional comments may be forthcoming.

If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 837-4956

C:\planning\grading\t07bu00156

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised site plan and additional requested documents
09/19/2007 ANDREW CONNOR NPPO REVIEW Approv-Cond NPPO needs review when returned from WWM
09/20/2007 JASON GREEN ENGINEERING REVIEW Denied DATE: September 21, 2007
SUBJECT: Bilby Industrial Site Plan- 4th Engineering Review
TO: MPE: Attn: Lisa Bowers
LOCATION: 2622 E Bilby Rd, T15S R14E Sec08 Ward 5
REVIEWERS: Jason Green, CFM
ACTIVITY: T07CM00265 (Site Plan) and T07BU00156 (Grading Plan)


SUMMARY: Engineering Division of Development Services Department has received and reviewed the revised site plan (T07CM00265), grading plan (T07BU00156), Drainage Report (CMG Drainage Engineering, LLC, dated 24APR07 and addendum 23AUG07), Phase I Drainage Report (CMG Drainage Engineering, LLC, dated 12MAY04), Geotechnical Addendum (Western Technology, Inc., dated 16APR07), Declaration and Establishment of Protective Covenants, Conditions, and Restriction (Docket 13029, Page 5355), Agreement Package, and Stormwater Pollution Prevention Plan (SWPPP). The site plan and grading plan are not approved at this time. Please address the following comments:


SITE PLAN COMMENTS:

1) DS Sec.10-02.2.3.1.5: The proposed Agreement Package from the adjacent property owner for the use of the proposed offsite detention basin B and all drainage improvements located on Lot 1 addresses the use and maintenance of the offsite improvements. However this document must be signed, notarized and recorded prior to site plan approval. Provide the recorded document at resubmittal for site plan approval. Provide a note on the site plan that addresses this Agreement and the maintenance of all drainage improvements.

2) DS Sec.2-02.2.1.A.32: The revised Detail 2 on Sheet C4 does not show the minimum inside clear dimension of 10 feet by 20 feet between the steel bollards that are required between the container and the enclosure's rear and sidewall (refer to redlines on sheet C4 for clarification). The 10-foot dimension from the enclosure gate must be to the front of the back bollards not the CMU wall, revise.

3) Review and approval from TDOT Permits and Codes for all improvements within the public right-of-way will be required. A right-of-way use permit application will be required prior to construction. Refer to the following links for TDOT Forms and applications:

a) http://www.tucsonaz.gov/dsd/Forms_Fees___Maps/Applications/applications.html /
b) http://www.dot.ci.tucson.az.us/engineering/pia.php
c) Or contact Steve Tineo at 741-3115 for all additional questions regarding r-o-w.


GRADING PLAN: Be advised that the grading plan can not be approved prior to site plan approval. All comments associated with the site plan must be submitted for review and the site plan must be approved prior to grading plan approval.

4) DS Sec.10-02.10.9.1.8: Revise Detail 2 on Sheet C3 to call out the Standard Public Improvement Detail for the proposed typical riser type clean out with the cast iron cover. Show all details and dimensions for this transition from the 18-inch to 24-inch storm drain. Provide the concrete thickness around the pipes; dimension the width and depth of the chamber along with the distance between top of storm drain and the bottom of the cast iron cover.


STORMWATER POLLUTION PREVENTION PLAN COMMENTS: The SWPPP and exhibits prepared by CMG Drainage Engineering Inc, dated 24AUG07 have addressed all comments from my previous comment letter. The 3 copies of the SWPPP and exhibits must be returned with the site plan and grading plan submittal for stamped approval.


GENERAL COMMENTS:

Please provide a revised site plan, a revised grading plan, and the 3 SWPPP copies that address the comments provided above. For expedite purposes the site plan and grading plan can be reviewed over the counter for stamp approval once all items have been addressed.

For any questions or to schedule a meeting, call me at 837-4929.


Jason Green, CFM
Senior Engineer Associate
Engineering Division
Development Services

Final Status

Task End Date Reviewer's Name Type of Review Description
10/03/2007 THAUSER1 OUT TO CUSTOMER Completed
10/03/2007 THAUSER1 REJECT SHELF Completed