Review Details: GRADING
Permit Number - T07BU00008
Review Name: GRADING
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
01/03/2007 | KAROL ARAGONEZ | ZONING | REVIEW | Denied | DSD TRANSMITTAL FROM: Karol Aragonez Planner PROJECT: T07BU00008 7150 East 22nd Street Grading TRANSMITTAL DATE: January 4, 2007 COMMENTS: Please resubmit revised drawings along with redlines and a response letter, which states how all Zoning Review Section comments regarding the Land Use Code and Development Standards were addressed. 1. The grading plan has been reviewed by Zoning Review Section but cannot approve the plan until it has been approved by the Engineering, and Landscape Review Sections and until all zoning comments or concerns have been addressed. 2. Zoning will re-review the grading plan on the next submittal to ensure compliance with the approved and stamped site plan. Additional comments may be forthcoming. If you have any questions about this transmittal, please call Karol Aragonez, (520) 791-5550. S:\zoning review\planning\site review\T07BU00008.doc RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Approved site plan, grading plan and additional requested documents |
01/04/2007 | MATT FLICK | ENGINEERING | REVIEW | Denied | DSD Engineering Comments for Desert Toyota 1st Submittal DSD Engineering Offers The Following Comments: 1. Place the cut and fill quantities in the General Notes. 2. The Project Activity Numbers are T07BU00008 (grading) and T07CM00016 (site). 3. Place the site address in the address block 4. Page 6 - Fill in the data for the storm drain cleanouts. 5. Page 6 - Roof drains should not discharge onto the pedestrian circulation area. 6. Page 6 - Portions of the storm drain within the public drainage easement shall be of material acceptable to the City Engineer. Steel or corrugated metal pipe is not an acceptable material. 7. Page 7 - Portions of the storm drain within the public drainage easement shall be of material acceptable to the City Engineer. Steel or corrugated metal pipe is not an acceptable material. 8. Page 12 - Please check the values for Concentration Point OS1 (see drainage report comments). 9. Sheet 13 - Please fill in the data where "XX" is shown. 10. A SWPPP is necessary for disturbance of more than 1 acre. A Floodplain Use Permit application ($50 for application, + $150 for drainage report) is necessary. The grading permit will not be issued prior to approval of the floodplain permit. |
01/16/2007 | JOE LINVILLE | NPPO | REVIEW | Denied | 1) Revise the grading plan to include water harvesting areas for the street landscape borders. Grading, hydrology, and landscape structural plans are to be integrated to make maximum use of site storm water runoff for supplemental on-site irrigation purposes. LUC 3.7.4.3.B Revise the drainage design to allow for retention of stormwater in landscape basins. 2) Submit the approved site plans including landscape plans. Review of the grading plan will be based upon the approved plans and other applicable City regulations. |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
01/29/2007 | DELMA ROBEY | APPROVAL SHELF | Completed |
01/29/2007 | DELMA ROBEY | OUT TO CUSTOMER | Completed |
01/29/2007 | GERARDO BONILLA | REJECT SHELF | Completed |