Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Plan Number: T06PI00042
Parcel: Unknown

Address:
1979 E AJO WY

Review Status: Completed

Review Details: PIA RESUBMITTAL

Plan Number - T06PI00042
Review Name: PIA RESUBMITTAL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
01/12/2007 ASHOFFS1 ENGINEERING REVIEW Passed
01/12/2007 ASHOFFS1 UTILITY CLEARANCES COT STREETS DIVISION Denied SUBMIT UTILITY CLEARANCE LETTERS.
01/12/2007 ASHOFFS1 UTILITY CLEARANCES COT WATER NEW DEVELOPMENT Denied SUBMIT UTILITY CLEARANCE LETTERS.
01/12/2007 ASHOFFS1 UTILITY CLEARANCES PC WASTEWATER MGMT Denied SUBMIT UTILITY CLEARANCE LETTERS.
01/12/2007 ASHOFFS1 UTILITY CLEARANCES QUEST COMMUNICATION Denied SUBMIT UTILITY CLEARANCE LETTERS.
01/12/2007 ASHOFFS1 UTILITY CLEARANCES TUCSON ELECTRIC POWER CO Denied SUBMIT UTILITY CLEARANCE LETTERS.
01/12/2007 ASHOFFS1 UTILITY CLEARANCES COX COMMUNICATION Denied SUBMIT UTILITY CLEARANCE LETTERS.
01/12/2007 ASHOFFS1 UTILITY CLEARANCES SOUTHWEST GAS CORP Denied SUBMIT UTILITY CLEARANCE LETTERS.
01/12/2007 ASHOFFS1 UTILITY CLEARANCES EL PASO NATURAL GAS Denied SUBMIT UTILITY CLEARANCE LETTERS.
01/12/2007 ASHOFFS1 UTILITY CLEARANCES KINDER MORGAN ENERGY Denied SUBMIT UTILITY CLEARANCE LETTERS.
01/22/2007 GARY WITTWER DOT LANDSCAPE REVIEW Denied Still no NPPO submittal.
02/08/2007 JOSE ORTIZ DOT TRAFFIC REVIEW Approv-Cond February 8, 2007
ACTIVITY NUMBER: T06PI00042
PROJECT NAME: Southgate Business Park
PROJECT ADDRESS: 1979 E Ajo Way
PROJECT REVIEWER: Jose E. Ortiz PE, Traffic Engineer

Resubmittal Required: Traffic Engineering recommends a conditional approval of the PIA Plan.

The following items must be revised or added to the plan. Provide a PDF of the revised drawing to verify that the following items have been addressed prior to submitting the mylar drawings.

1. See redlines on the submitted drawings and address the additional redline comments.

2. Sheet 6 of 7: In error Rick Engineering was instructed to install a 'RIGHT LANE' (R3-5F) supplemental plaque under all new (R3-5R) along all proposed right turn bays. These plaques are not required under the two proposed stop signs. See Redlines for clarification.

3. Sheet 6 of 7: In error Rick Engineering was instructed to install an R6-1(R) "ONE WAY" Sign in the median at both driveway locations along Ajo Way. Since these are driveways the one way signs are not required. Please remove the proposed one way signs from the striping plan. See redlines for clarification.

4. Sheet 6 of 7: Provide an object marker (OM2-2V(AD) in the bull nose at the southern Kino driveway per PCDOT & TDOT Signing Manual (2002) section 9-17.



If you have any questions, I can be reached at 791-4259 x 76730 or Jose.Ortiz@tucsonaz.gov
02/12/2007 ASHOFFS1 PIA COORDINATOR CUSTOMER CALLED; PLANS @ AMBASSADOR Completed
02/12/2007 LANCE PETERSON DOT STREET MAINTENANCE REVIEW Approved
02/12/2007 RICHARD LEIGH DOT ENGINEERING REVIEW Approv-Cond Ok to submit mylars for final approval and signing after final plat recorded.

Additionally, a detailed itemized bid estimate for all the proposed improvements in the public ROW, excluding wet and dry utilities, will have to be submitted to this office for review. The bid estimate must include item description, item quantity, unit cost, unit cost total and a grand total for the materials, labor, and all other related costs, including all applicable taxes.
02/12/2007 ASHOFFS1 PIA COORDINATOR OUT TO CUSTOMER Completed