Plan Review Detail
Review Status: Completed
Review Details: PIA RESUBMITTAL
Plan Number - T06PI00023
Review Name: PIA RESUBMITTAL
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
08/01/2006 | TAMI HAUSER | ENGINEERING | REVIEW | Needs Review | |
08/01/2006 | TAMI HAUSER | UTILITY CLEARANCES | COT STREETS DIVISION | Completed | |
08/01/2006 | TAMI HAUSER | UTILITY CLEARANCES | COT WATER NEW DEVELOPMENT | Completed | |
08/17/2006 | GARY WITTWER | DOT LANDSCAPE | REVIEW | Denied | Please submit a copy of you Landscape and Irrigation plan for common area A. Private irrigation lines can not be placed under public roadways. |
08/17/2006 | JOSE ORTIZ | DOT TRAFFIC | REVIEW | Approved | |
08/22/2006 | TAMI HAUSER | UTILITY CLEARANCES | PC WASTEWATER MGMT | Completed | |
08/22/2006 | TAMI HAUSER | UTILITY CLEARANCES | QUEST COMMUNICATION | Completed | |
08/22/2006 | TAMI HAUSER | UTILITY CLEARANCES | TUCSON ELECTRIC POWER CO | Completed | |
08/22/2006 | TAMI HAUSER | UTILITY CLEARANCES | COX COMMUNICATION | Passed | |
08/22/2006 | TAMI HAUSER | UTILITY CLEARANCES | SOUTHWEST GAS CORP | Completed | |
08/22/2006 | TAMI HAUSER | UTILITY CLEARANCES | EL PASO NATURAL GAS | Completed | |
08/22/2006 | TAMI HAUSER | UTILITY CLEARANCES | KINDER MORGAN ENERGY | Passed | |
08/28/2006 | LANCE PETERSON | DOT STREET MAINTENANCE | REVIEW | Denied | We have reviewed these plans and have the following comments: Landscaping 1. Sheet 2 of 12 - Note 23- Please correct Paul Rosenboom's extension to 234. 2. Please provide the proposed landscape plan for the landscape areas within the right of way that the City will be responcible for maintaining. This plan should be directed to Paul Rosenboon at 4004 S. Park Avenue - Phone 791-3154 ext 234. No further comments. 8/28/06 |
08/30/2006 | Estevan Tineo | DOT ENGINEERING | REVIEW | Denied | La Estancia De Tucson, Lots 331-410 The following comments, at a minimum, must be addressed in the submittal. 1. Sheet 2 of 12: Provide the Floodplain Use Permit number. Note, this permit should cover all floodplains, including related drainage infrastructure in the r/w. 2. Sheet 3 of 12: Detail B, Add "NO PARKING" in the PAD description. 3. Sheet 3 of 12: Detail C, Add "NO PARKING" and "4'-SIDEWALK" in the PAD description. 4. Sheet 4 of 12: Detail C, provide rectangular concrete transition. 5. Sheet 4 of 12: Detail C, no gutter depression in pavement section, this includes the bike lane. Please revise. 6. Sheet 4 of 12: Detail B, is proposed catch basin behind curb line? Will this type of design convey drainage on a continuous grade? 7. Sheet 6 of 12: The plans must refer to paving plans (I-2006-####) not plan review tracking numbers (T06PI-####), please revise accordingly. 8. General Comment: Given that this project (La Estancia) contains phases that depend on other phases, add the following note (or something similar): PIA Paving Plan I-200#-####, I-200#-####,..etc., as applicable must be installed and accepted prior to the construction of these improvements. 9. Sheet 7 of 12: Please indicate the appropriate paving plan numbers, not pia tracking numbers, for those items to be built on other plans (Typical). 10. Sheet 8 of 12: Plan indicates an existing RCP? And with less than 12" of cover? Please indicate the PIA Paving Plan number for the RCP to be built and make sure the pipe (and all other pipes) have adequate cover, the pipe crown must be below the pavement section. 11. Previous comment 20. Please note, A CLOMR must be obtained for FEMA floodplains prior to construction in FEMA floodplain. Revise plans accordingly. |
09/01/2006 | THAUSER1 | CONSTRUCTION ESTIMATE | REVIEW | Needs Review | |
09/01/2006 | TAMI HAUSER | PIA COORDINATOR | CUSTOMER CALLED; PLANS @ AMBASSADOR | Completed | |
09/01/2006 | TAMI HAUSER | PIA COORDINATOR | OUT TO CUSTOMER | Completed |