Plan Review Detail
Review Status: Completed
Review Details: PIA RESUBMITTAL
Plan Number - T06PI00016
Review Name: PIA RESUBMITTAL
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
09/14/2006 | Estevan Tineo | DOT ENGINEERING | REVIEW | Approv-Cond | 0/9/2006: T06PI00016: (Please note it's the responsibility of the Design Engineer - Castro Engineer - to prepare plans in accordance to all applicable Standards and Ordinances, any issues encountered during construction shall be addressed by the Engineer - in this case Castro Engineer - at no cost to the City). Conditional approval on the following conditions: 1. Sheet 1 of 26: Please add book and page. 2. Sheet 4 of 26: Detail I, minimum slope for S3 is 1% and 2% max., revise. 3. Sheet 4 of 26: Detail I, Detail 205.5 indicates 3.5% for S1, revise. 4. Sheet 4 of 26: Detail H, no warp, 12:1 max, revise. Note: Per your comment response letter, Previous gutter depression (previous comment 4 ) in Bike Lane approved by COT DOT Capital section Manager Andy McGovern. |
10/02/2006 | GARY WITTWER | DOT LANDSCAPE | REVIEW | Approv-Cond | The plans are approved. Please have the developer submit a letter of understanding to the City that the landscape and irrigation installed by the developer within the ROW will be maintained by the developer or HOA. |
10/09/2006 | THAUSER1 | CONSTRUCTION ESTIMATE | REVIEW | Needs Review | |
10/13/2006 | LANCE PETERSON | DOT STREET MAINTENANCE | REVIEW | Approved | |
10/27/2006 | TAMI HAUSER | PIA COORDINATOR | CUSTOMER CALLED; PLANS @ AMBASSADOR | Completed | |
10/27/2006 | TAMI HAUSER | ENGINEERING | REVIEW | Completed | |
10/27/2006 | TAMI HAUSER | PIA COORDINATOR | OUT TO CUSTOMER | Completed |