Permit Review Detail
Review Status: Completed
Review Details: POST 3RD PARTY REVIEW
Permit Number - T06CM06327
Review Name: POST 3RD PARTY REVIEW
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
08/28/2007 | JOHN WILLIAMS | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Completed | Impact Fee's Do Apply; East District; 3,104 Square Feet of Office; $7381.65 |
08/28/2007 | DAVE MANN | FIRE | REVIEW | Denied | Note regarding FM 200 system on sheet P1.8 is incorrect. Wet pipe sprinkler system is required in all parts of all buildings. The FM 200 system can be installed in addition to the wet system, and be designed to activate before the wet pipe system, but the wet system will always be required. Please revise note on sheet P1.8. |
08/28/2007 | GERRY KOZIOL | WWM | REVIEW | Denied | NEEDS TO PERMIT POOL/RAMADA 1. LODGE ON THE DESERT 2. NEEDS TO BUILD PUBLIC SEWER PER DP #D06-0028- NEEDS PUBLIC SEWER CONSTRUCTION PERMIT & HOLD HARMLESS LETTER 3. NEEDS TO PERMIT ON - SITE PRIVATE SEWER - NEEDS DEQ REVIEW & APPROVAL TO CONSTRUCT - NEEDS COPY OF ON - SITE PRIVATE SEWER FOR BASE MAP UPDATE |
09/04/2007 | PATRICIA GILBERT | ENGINEERING | REVIEW | Denied | Provide two copies of the approved development plan, landscape and NPPO plans with the approved building plan set. A site application card (yellow card) with the CDRC approved development plan must be stamped with signatures for DSD site approval by the following reviewing sections; Fire, Zoning, Handi-cap, Engineering, Plumbing and Landscape/NPPO. The development plan may be walked through for stamps and site card sign off. No fees are involved in re-stamping the development/tentative plat plans as an approved site plan. This process must complete prior to building plan approved. The development plan stamped for site plan approval must acompany the building plan prior to building plan approval. |
09/10/2007 | HEATHER THRALL | ZONING | REVIEW | Denied | Zoning will continue the review of the building plan once Willdan approves the building plans and the development plan is approved. |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
09/20/2007 | CINDY AGUILAR | APPROVAL SHELF | Completed |
09/20/2007 | CINDY AGUILAR | OUT TO CUSTOMER | Completed |