Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Completed
Review Details: POST 3RD PARTY REVIEW
Permit Number - T06CM06322
Review Name: POST 3RD PARTY REVIEW
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
05/21/2007 | JOHN WILLIAMS | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Passed | |
05/21/2007 | ROBERT SHERRY | WATER | REVIEW | Approved | |
05/21/2007 | MARTIN BROWN | FIRE | REVIEW | Approved | |
06/02/2007 | PATRICIA GILBERT | ENGINEERING | REVIEW | Denied | An approved site plan is required prior to building plan approval. |
06/05/2007 | GERRY KOZIOL | WWM | REVIEW | Denied | 1:shell bldg #1includes model unit & 1-4" fs) 2: No TI's until sewer fees are paid 3: No waste water stub-outs with the exception of 1 toilet, 1 lav in model unit & 1-4"fs 4: need to permit on-site private sewer- over 3000 gal/day requires DEQ review & approval to construct 5: needs manhole construction permit 6: needs copy on-site private sewer for base map update |
06/11/2007 | HEATHER THRALL | ZONING | REVIEW | Denied | The site plan for this project has not been approved as of this review of the building plans. Please provide a copy of the approved site plan with the building plans and staff can proceed with further review. The building plans show a parapet of 22' which should be noted on the site plan as well. The building plans should be resubmitted. |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
06/13/2007 | CINDY AGUILAR | APPROVAL SHELF | Completed |
06/13/2007 | CINDY AGUILAR | OUT TO CUSTOMER | Completed |