| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 07/19/2007 | DAVE MANN | FIRE | REVIEW | Approved | |
| 08/01/2007 | WILLDAN | ENGINEERING | REVIEW | Denied | July 30, 2007 City of Tucson Development Services P.O. Box 27210 Tucson, AZ 85726 RE: ALL STAR AUTO EXCHANGE REVISION – 1ST REVIEW CITY OF TUCSON LOG NO. T06CM05961-R2 WILLDAN PROJECT NO. 16608-7005 The initial review for the above project has been completed. This letter contains comments which need to be addressed by written responses to each which indicate any actions taken. In order to facilitate a shorter second review, all corrections and revisions must be made on the original plans and two complete new sets of prints, along with one complete redlined set, must be returned to our office. To avoid delays, ensure that all corrections have been made, are complete, and have been coordinated on all applicable detail and note sheets. Pen or pencil corrections on final prints are not acceptable. Should you have questions regarding the comments herein, please contact your plans examiners, David Gue. ENGINEERING COMMENTS: SHEET C2.1 Add As Built Certification (see attached). Paving & Grading Notes – Note (9) – Add contact permits and codes at (520) 791-5100 for permit information. SHEET C2.2 Add section from display area to the public alley. Provide a section through the proposed scuppers extending beyond the openings at the base of the wall. Please provide finished surface elevations at locations shown on the redlines. Please provide flow line elevations at the base of the wall and at the scupper locations. Provide Typical Section for the 6” depressed landscape areas. Please define the disposition of the runoff from the display area after it reaches the outlet at the base of the wall. At the southwest project corner, add match existing and begin new 5’ concrete sidewalk. SHEET C1.1 Please note the word “exchange” in the project title is misspelled. SHEET C1.1F Same as Sheet C1.1-1 above. Sincerely, WILLDAN David P. Gue, P.E. Supervising Engineer DPG/jk |
| 08/08/2007 | ANDREW CONNOR | NPPO | REVIEW | Approved | |
| 08/08/2007 | ANDREW CONNOR | LANDSCAPE | REVIEW | Approved | |
| 08/08/2007 | WILLDAN | ZONING HC SITE | REVIEW | Approved | |
| 08/16/2007 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Passed | |
| 08/22/2007 | WILLDAN | ZONING | REVIEW | Approved |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 08/22/2007 | SUE REEVES | OUT TO CUSTOMER | Completed |
| 08/22/2007 | SUE REEVES | REJECT SHELF | Completed |