Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Number: T06CM05602
Parcel: 116300530

Review Status: Completed

Review Details: RESUBMITTAL

Permit Number - T06CM05602
Review Name: RESUBMITTAL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
01/12/2007 JOE LINVILLE NPPO REVIEW Denied 1) Provide documentation that the proposed conservation easement has been recorded. LUC 3.8
Note the recording on the site/grading plan. Draw the easement on the site plan.

2) Add the following Hillside Development Zone notes to the site/grading plan:

A. Vegetation Retention.

1. Existing trees with four (4) inch or greater trunk diameter and cacti will be preserved in their original locations, except for building sites and access and utilities serving building sites.

2. When retention of the above trees and cacti in their original locations is not possible due to building site location, the trees and cacti will be salvaged and replanted in areas requiring re-vegetation, whenever possible.

B. Re-vegetation. All cut or fill slopes, which are no steeper than three (3:1) and all utility trenches or septic leaching fields which are not located in parking or driveway areas will be re-vegetated in compliance with the following requirements.

1. All plants used in re-vegetation must be the same as the native vegetation on the site or any adjacent site prior to grading or clearing.

2. Re-vegetation will be accomplished with the following minimum requirements for plants.

a. Native trees, a minimum of fifteen (15) gallon size with a minimum trunk diameter of two (2) inches measured at the soil level, or large specimen cactus will be placed at the same vegetation density found on the site prior to any clearing, grubbing, or grading.

b. Seeds for trees, desert shrubs, and grasses will be planted with a density adequate to control erosion and may use one of the following methods of planting or any other method approved by the Zoning Review Section at DSD.

1) Raked into the soil with appropriate mulch materials;
2) Hydro-seeding;
3) Anchored mulches; or
4) Established on jute, rolled straw, or similar material.

C. A temporary watering system must be installed until the re-vegetation materials is established.

D. Fencing shall be required during construction per DS 2-06.8.0 Fig.1 for all undisturbed natural desert areas of Protected Native Plants and for individual Protected Native Plants to be preserved-in-place. The area to be fenced shall be beyond the "drip-line" of the vegetation by one-half (½) the distance of the "drip-line" radius. For Saguaros and cacti, the area to be fenced shall be equal to the distance of one-half (½) the height of the plant per DS 2-15.6.0

E. NPPO pre permit inspection is required prior to grading inspection can be scheduled by calling IVR system and entering inspection code 09015 or calling Landscape Field Representative directly @ 791-5550 EXT 1140

F. Grubbing, grading, and clearing are to occur only within the areas identified on the grading plan and staked on the site or lot. The limits should include all cut and fill areas, leach fields, septic tanks and future development areas identified

G. The portions of the site or lot to be left ungraded are to remain undisturbed and are not to be used for stockpiling of materials or excess fill, construction vehicle access, storage of vehicles during construction, or similar uses.

H. Development other than hiking trails will not be permitted within the legally described boundaries of the natural area.

3. Include the location, size, color, and textural treatment of all retaining walls, riprapped slopes, or other constructed means of slope stabilization must be shown on one (1) of the plans submitted. Vegetation retention and re-vegetation should be used in conjunction with riprapping.