Permit Number: T06CM05564
Parcel: 13217118C

Review Status: Completed

Review Details: CELL TOWER/ANTENNAS

Permit Number - T06CM05564
Review Name: CELL TOWER/ANTENNAS
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
10/24/2006 DAVE MANN FIRE REVIEW Approved
10/30/2006 PETER MCLAUGHLIN PLANNING-CITY HALL REVIEW Approved
11/01/2006 TERRY STEVENS ZONING REVIEW Denied Building plans cannot be approved until the site plan has been stamped and approved.
11/07/2006 LINDA BUCZYNSKI ELECTRICAL-COMMERCIAL REVIEW Approved
11/20/2006 JAY HOGAN COMMUNICATIONS REVIEW Approved
12/05/2006 CHRISTY FOREMAN BUILDING-COMMERCIAL REVIEW Denied CITY OF TUCSON DEVELOPMENT SERVICES
STRUCTURAL REVIEW COMMENTS

DATE: 12-6-06
ACTIVITY NUMBER: T06CM05564
PROJECT NAME: New Cell Tower
PROJECT ADDRESS: 1021 E. Palmdale St.
ARCHITECT / ENGINEER: TDE
PROJECT REVIEWER: Christy Foreman


TRANSMIT ORIGINAL DRAWINGS WITH NEXT SUBMITTAL.

PLEASE CALL AT 791-5550 X1108 OR EMAIL AT CHRISTY.FOREMA1@TUCSONAZ.GOV IF YOU CARE TO DISCUSS.

1) 1997 Uniform Administrative Code - section 302.5 Inspection and Observation Program. When special inspection is required by Section 306, the architect or engineer of record shall prepare an inspection program which shall be submitted to the building official for approval prior to issuance of the building permit. The inspection program shall designate the portions of the work to have special inspection, the name or names of the individuals or firms who are to perform the special inspections and indicate the duties of the special inspectors.

The special inspector shall be employed by the owner, the engineer or architect of record, or an agent of the owner, but not the contractor or any other person responsible for the work.

When structural observation is required by Section 307, the inspection program shall name the individuals or firms who are to perform structural observation and describe the stages of construction at which structural observation is to occur.

The inspection program shall include samples of inspection reports and provide time limits for submission of reports.


2) Provide Connector details for antenna attachments to monopole. Justify connections with structural calculations.
3) Clarify / specify per the structural calculations each pole section dimensions. Provide pole specifications on drawings per structural engineer calculations.
4) Clarify / specify on drawings base plate and bolt type on drawings per the structural engineers calculations.

Final Status

Task End Date Reviewer's Name Type of Review Description
12/19/2006 DELMA ROBEY OUT TO CUSTOMER Completed
12/19/2006 SUE REEVES REJECT SHELF Completed