Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Completed
Review Details: POST 3RD PARTY REVIEW
Permit Number - T06CM05072
Review Name: POST 3RD PARTY REVIEW
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
11/17/2006 | VFLORES1 | 3RD PARTY REVIEW-COMMERCIAL | REVIEW | Completed | |
11/17/2006 | ROBERT SHERRY | WATER | REVIEW | Approved | |
11/17/2006 | VFLORES1 | 3RD PARTY REVIEW-COMMERCIAL | AT 3RD PARTY OFFICE | Approved | |
11/19/2006 | MARTIN BROWN | FIRE | REVIEW | Approved | |
11/20/2006 | GERRY KOZIOL | WWM | REVIEW | Denied | needs to permit on-site private sewer- needs DEQ approval if over 3000 gal/day- needs to abandone exsisting 8" public sewer with exsisting public sewer easment- needs manhole construction permit(8th floor review-5th floor permit) - needs 8th floor review (plan & profile public sewer drawings do not agree with map guide sewer information)- needs copy of private sewer drawings for base map update. |
11/22/2006 | STEVE SHIELDS | ZONING | REVIEW | Denied | 11/22/06 Development Services Department Zoning Review Section Steve Shields Lead Planner Comments: T06CM05066, 5061, 5068, 5069, 5070, 5071, 5072 - Building plan review 1. The building plan has been reviewed by Zoning Review Section but cannot approve the plan until it has been approved by the Engineering, and Landscape Review Sections and until all zoning comments or concerns have been addressed. 2. Zoning could not verify that the building plan was in compliance with the approved site plan. Please submit two copies of the approved and stamped site/development, landscape, and NPPO plans with the next building plan submittal. A site card with DSD approvals by Fire, Zoning, Handi-cap, Engineering, and Landscape/NPPO including the approved development/tentative plat plans stamped for site plan approval and signatures is required before the building plan can be approved by Zoning. Two copies of the approved site/development plan, landscape and NPPO plans are to be submitted with the building plans packet for processing and approval as a site plan. No fees are involved in re-stamping the development/tentative plat plans as an approved site plan. Submit the following: two copies of the stamped development plan, landscape and NPPO plans must be included with the site plans packet processed together for site approval. 3. Zoning will re-review the building plan on the next submittal to insure compliance with the approved site/development plan. Additional comments may be forthcoming. If you have any questions about this transmittal, please call Steve Shields, (520) 791-5608 ext. 1180. C:\planning\building\t06cm05066.doc |
11/22/2006 | BETSY COTTLE | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Passed | |
12/07/2006 | PAUL MACHADO | ENGINEERING | REVIEW | Approved |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
12/20/2006 | FSANCHE1 | OUT TO CUSTOMER | Completed |
12/20/2006 | SUE REEVES | REJECT SHELF | Completed |