Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL TI
Permit Number - T06CM04622
Review Name: COMMERCIAL TI
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 08/17/2006 | MARTIN BROWN | FIRE | REVIEW | Approved | |
| 08/17/2006 | LINDA BUCZYNSKI | ELECTRICAL-COMMERCIAL | REVIEW | Denied | T06CM04622 8/17/06 1. Provide a maintenance receptacle for the Heat Pump. Reference NEC 210.63. 2. Provide a lighting fixture schedule. 3. Demonstrate compliance with the Tucson Lighting Code. 4. Provide available fault current at the electrical service. 5. Provide fault current rating of new panel. 6. Demonstrate that new panel is installed within its fault current rating. 7. Bathroom receptacles for each bathroom shall supply no other outlet. Reference NEC 210.11 (C) (3). 8. Bedroom branch circuits shall have AFCI. Reference NEC 210.12. 9. Meet receptacle spacing requirements per NEC 210.52 (A) (1). 10. Meet receptacle spacing requirements per NEC 210.52 (C) (1). |
| 08/17/2006 | CHRISTY FOREMAN | BUILDING-COMMERCIAL | REVIEW | Approved | |
| 08/21/2006 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | Minimum font size 1/8" |
| 08/21/2006 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | 1. Revise drawings for legibility, minimum font size of 1/8", and show riser diagrams for the waste and water supply systems. 2. Show that the shower valve is pressure balanced. 3. Show how the hot water temperature to the shower is to be limited to 120 degrees Fahrenheit. (The thermostat of the water heater may not be used to assure the maximum temperature.) 4. Show how the T&P relief for the water heater can be routed to the outside of the building. |
| 08/21/2006 | ROBERT SHERRY | WATER | REVIEW | Denied | Show that a backflow protection valve is not required for this building. |
| 09/01/2006 | CAGUILA1 | ZONING | REVIEW | Needs Review | |
| 09/01/2006 | CAGUILA1 | WWM | REVIEW | Needs Review | |
| 09/01/2006 | BETH GRANT | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Needs Review | |
| 09/01/2006 | ANY | ENGINEERING | REVIEW | Approved |