Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Number: T06CM04508
Parcel: 117061900

Review Status: Completed

Review Details: COMMERCIAL TI

Permit Number - T06CM04508
Review Name: COMMERCIAL TI
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
08/09/2006 HEATHER THRALL ZONING REVIEW Approved
08/09/2006 ROBERT SHERRY MECHANICAL-COMMERCIAL REVIEW Denied Provide structural calculations to verify that the existing roof is capable of supporting the additional dead load due to the installation of the roof top unit. Reference Section 302.1, IMC 2003.
08/09/2006 LINDA BUCZYNSKI ELECTRICAL-COMMERCIAL REVIEW Denied T06CM04508 8/9/10

City does not allow current limiting characteristics of line side OCPDs to attenuate fault current at new electrical panels. It appears that AFC at new Panel A is 11, 588A. Suggest rating of 14K.
08/09/2006 ROBERT SHERRY WATER REVIEW Approved
08/09/2006 CHRISTY FOREMAN BUILDING-COMMERCIAL REVIEW Denied 1) Provide structural calculations to verify that the existing roof is capable of supporting the additional dead load due to the installation of the roof top unit. Reference Section 302.1, IMC 2003.
2) Clarify sq. footage of suite.
3) Clarify occuancy of basement.
4) Clarify separated use / fire walls.
5) Location of address is not as shown on bldg site plan. Please clarify.
08/09/2006 SUZANNE BOHNET ENGINEERING REVIEW Approved
08/09/2006 ROBERT SHERRY PLUMBING-COMMERCIAL REVIEW Denied 1. Show how the temperature of the hot water supply to the public lavatory controlled. Reference Section 414.1, UPC 2003 and Section 804.3, IECC 2003.
2. Show the size, route and termination of T&P relief piping. Reference Section 608.5, UPC 2003.
3. All storage-type water heaters installed in a closed system require a listed expansion tank. Please show expansion tanks on plans. Reference Section 608.3, UPC 2003 with local amendments.
4. Clarify the routing of the main building drain and show its size. (Note that the site key plan shows the project at the wrong location)
09/19/2006 GBONILL1 WWM REVIEW Needs Review
09/19/2006 GBONILL1 FIRE REVIEW Needs Review
09/19/2006 BETH GRANT COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Needs Review