Permit Number: T06CM04395
Parcel: 10309068D

Review Status: Completed

Review Details: POST 3RD PARTY REVIEW

Permit Number - T06CM04395
Review Name: POST 3RD PARTY REVIEW
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
09/07/2006 BETSY COTTLE COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Passed
09/07/2006 ROBERT SHERRY WATER REVIEW Approved
09/07/2006 MARTIN BROWN FIRE REVIEW Approved
09/18/2006 GERRY KOZIOL WWM REVIEW Denied needs 8th floor review of easement & joint use agreements if applicable
09/19/2006 JASON GREEN ENGINEERING REVIEW Needs Review This building permit is associated with Development Plan # D01-0013. D01-0013 has been denied and is waiting for supplemental information to be submitted before approval.
09/21/2006 TERRY STEVENS ZONING REVIEW Denied 09/21/06

Development Services Department
Zoning Review Section

Terry Stevens
Lead Planner

Comments for T06CM04395:

1. The building plan has been reviewed by Zoning Review Section but cannot approve the plan until it has been approved by the Engineering, and Landscape Review Sections and until all zoning comments or concerns have been addressed.

2. Zoning could not verify that the building plan was in compliance with the approved development plan. Please submit two copies of the approved and stamped development, landscape, and NPPO plans with the next building plan submittal.

3. Zoning will re-review the building plan on the next submittal to insure compliance with the approved site/development plan. Additional comments may be forthcoming.

4. A site card with DSD approvals by Fire, Zoning, Handi-cap, Engineering, and Landscape/NPPO including the approved development plan stamped for site plan approval and signatures is required before the building plan can be approved by Zoning. Two copies of the approved development plan, landscape and NPPO plans are to be submitted with the building plans packet for processing and approval as a site plan. No fees are involved in re-stamping the development/tentative plat plans as an approved site plan. The development plan may be walked through for stamps and site card sign off. Submit the following: two copies of the stamped development plan, landscape and NPPO plans must be included with the building plans packet processed together for site approval

Final Status

Task End Date Reviewer's Name Type of Review Description
02/12/2007 DELMA ROBEY OUT TO CUSTOMER Completed
02/12/2007 SUE REEVES REJECT SHELF Completed