Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL
Permit Number - T06CM04299
Review Name: RESUBMITTAL
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
04/02/2007 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | Provide the size of the reduced pressure backflow preventer assembly. Reference Section 103.2.3, UPC 2003. |
04/02/2007 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Approved | |
04/04/2007 | STEVE SHIELDS | ZONING | REVIEW | Denied | DSD TRANSMITTAL FROM: Steve Shields Lead Planner PROJECT: Southgate Business Park T06CM04297, T06CM04298, T06CM04299, T06CM04300, T06CM04301 Building Plan TRANSMITTAL DATE: April 4, 2007 1. The building plan has been reviewed by Zoning Review Section but cannot approve the plan at this time. 2. Zoning could not verify that the building plan was in compliance with the approved site plan. The tentative plat/development plan has been revised and is currently under review. The revised tentative plat/development plan, once approved, must be approved as a site plan. The review for a tentative plat/development plan to a site plan can be done as a walk through. Once the site plan has been approved include two (2) copies of the approved site plan with your next building plan submittal. Please submit two copies of the approved and stamped site, landscape, and NPPO plans with the next building plan submittal. 3. Due to the rezoning the site plan and building plans cannot be approved until 30 days following the approval of the final plat. 4. Zoning will re-review the building plan on the next submittal to insure compliance with the approved and stamped site plan. Additional comments may be forthcoming. If you have any questions about this transmittal, please call Steve Shields, (520) 837-4956 C:\planning\building\t06cm04297-3rd.doc RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Approved and stamped site plan and additional requested documents |
04/10/2007 | GERRY KOZIOL | WWM | REVIEW | Denied | 1) SHELL BLDG #3 ONLY-NEEDS TO PERMIT PRIVATE SEWER FOR SOUTHGATE BUSINESS PARK- LOTS #1-#5 (BUILDINGS #1 TO #6) PERMIT pt06s04668. 2) NEEDS WW/DSC 1ST FLOOR HOLD HARMLESS LETTER TO CONNECT TO PRIVATE SEWER WHICH CONNECTS TO A PUBLIC. WHICH HAS NOT BEEN RELEASED & ACCEPTED BY PCWWM-740-6503 |
04/18/2007 | PATRICIA GILBERT | ENGINEERING | REVIEW | Approved | |
04/19/2007 | LINDA BUCZYNSKI | ELECTRICAL-COMMERCIAL | REVIEW | Approv-Cond | Electrical Plans Examiner will sign title sheet when all approved electrical sheets are conbined into the latest set. |
04/19/2007 | CHRISTY FOREMAN | BUILDING-COMMERCIAL | REVIEW | Approved |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
04/26/2007 | DELMA ROBEY | OUT TO CUSTOMER | Completed |
04/26/2007 | SUE REEVES | REJECT SHELF | Completed |