Permit Review Detail
Review Status: Completed
Review Details: COMMERCIAL-BLDG/FIRE/ZONING/ENG
Permit Number - T06CM04105
Review Name: COMMERCIAL-BLDG/FIRE/ZONING/ENG
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
08/23/2006 | DAVE MANN | FIRE | REVIEW | Approved | |
08/28/2006 | BETSY COTTLE | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Passed | |
08/29/2006 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Approved | |
08/29/2006 | ROBERT SHERRY | WATER | REVIEW | Approved | |
09/11/2006 | LINDA BUCZYNSKI | ELECTRICAL-COMMERCIAL | REVIEW | Denied | TRANSMIT ORIGINAL DRAWINGS WITH NEXT SUBMITTAL. PLEASE CALL AT 791-5550 X1106 OR EMAIL AT Linda.Buczynski@tucsonaz.gov IF YOU CARE TO DISCUSS. 1. Reference Note 1A, replacement receptacles shall comply with NEC 406.3 (D), (b) or (c). 2. Reference Notes 1I and 1K, please perform this field check before submitting to design. Document any changes to electrical loads, conductor, and circuit breakers on the plans. 3. Provide power requirements for replacement AC units. Address overcurrent protection. |
10/03/2006 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | Previous plumbing permits to repair the gas lines and to replace the water heater were withdrawn or allowed to expire without inspection. Show the size, route, and loads of the natural gas supply piping at this address, specify the water heaters, and detail the installation of the water heaters. |
10/03/2006 | WILDAN | BUILDING-COMMERCIAL | REVIEW | Denied | October 2, 2006 City of Tucson Development Services 201 N. Stone Avenue Tucson, AZ 85701 RE: REPAIRS FOR SUNLAND MOTEL – 1ST REVIEW CITY OF TUCSON LOG NO. T06CM04093, T06CM04102, T06CM04103, T06CM04104, T06CM04105 WILLDAN PROJECT NO. 13881-6054 The initial review for the above project has been completed. This letter contains comments which need to be addressed by written responses to each which indicate any actions taken. In order to facilitate a shorter second review, all corrections and revisions must be made on the original plans and two complete new sets of prints, along with one complete redlined set, must be returned to our office. To avoid delays, ensure that all corrections have been made, are complete, and have been coordinated on all applicable detail and note sheets, and that all changes have been highlighted with appropriate revision numbers, revision dates, and “cloud bubbles.” Pen or pencil corrections on final prints are not acceptable. This project has been reviewed for conformance with the 2003 IBC, 1997 UAC, 2003 IMC, 2003 IECC, 2002 NEC codes with local modifications, and the 2003 UPC with State of Arizona Amendments. Any revisions to this plan will require an additional review and approval by Willdan. Should you have questions regarding the comments herein, please contact your plans examiner Chris Kiel. Occupancy Occup. Load Construction Area S.F. Sprinklered Alarms R-1 N/A VB N/A No No Special Inspection is required for the following items: N/A The following items are acceptable for deferred submittals: N/A GENERAL COMMENTS: General Please coordinate all of the information between the applications and the plans per Section 106.1.1 of the 2003 IBC as the permits appear to only address units 1-5, but the plans appear to address other units. Please clearly define all of the work to be done as part of these applications in accordance with Section 106.1.1 of the 2003 IBC. The plans reference structural repairs for the roof system, but fail to specify the size, species and grade of the joists, beams and columns. The plans denote the addition of gas shut-off valves, but the violation notice indicates that the permits for the water heaters either expired or were withdrawn, and therefore, needs to be addresses as part of this permit. Electrical work is referenced in the notes on Sheet A-3, but the specific information is not provided, i.e., no conductor or conduit size, no electrical load calculations, no circuit callouts, no panel locations, no equipment information, etc. Please dimension the plans in accordance with Section 106.1.1 of the 2003 IBC. ARCHITECTURAL COMMENTS: Sheet C Please coordinate the sheet index with the provided sheets per Section 106.1.1 of the 2003 IBC. Sheets A-2 & A-3 Please provide additional information regarding the A/C / Heater units per Section 106.1.1 of the 2003 IBC, i.e., unit size, weight, air flow volume, electrical demand, gas demand, etc. Please provide the detail regarding the opening for the A/C /Heater unit per Section 106.1.1 of the 2003 IBC. In addition, please indicate if the opening is larger or smaller than the existing opening. If so, then specify a new header per Section 1603.1 of the 2003 IBC. Please coordinate the detail callouts with the information provided within the plans per Section 106.1.1 of the 2003 IBC, i.e., Details A/D-3, B/D-3, F/D-3, etc. Please provide structural calculations for all repairs associated with the structural components per Section 106.1.1 of the 2003 IBC, i.e., beams, columns, joists, footings, lateral analysis (for the replaced areas), etc. In addition, please specify the typical soil bearing pressure. Please provide additional information regarding the emergency escape rescue windows and doors per Section 106.1.1 of the 2003 IBC, in order to verify compliance with Chapter 10 for all openings that have been modified. Please specify all equipment to be replaced per Section 106.1.1 of the 2003 IBC. STRUCTURAL COMMENTS: Sheets A-2 & A-3 Please specify the grade, species and size for all beams, joists, and columns per Section 106.1.1 of the 2003 IBC. PLUMBING COMMENTS: See City comments. MECHANICAL COMMENTS: See City comments. ELECTRICAL COMMENTS: See City comments. ENERGY CODE COMMENTS: Reviewed and accepted. ACCESSIBILITY COMMENTS: General Please provide verification that 20% of the remodeling costs associated with the primary function have been spent upgrading the accessibility for this project, in accordance with Section 3409.6 of the 2003 IBC. Sincerely, WILLDAN Martin Haeberle, C.B.O. Building Official MAH/tb |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
11/03/2006 | GERARDO BONILLA | OUT TO CUSTOMER | Completed |
11/03/2006 | SUE REEVES | REJECT SHELF | Completed |