Permit Review Detail
Review Status: Completed
Review Details: POST 3RD PARTY REVIEW
Permit Number - T06CM03798
Review Name: POST 3RD PARTY REVIEW
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 01/05/2007 | SUE REEVES | COMMERCIAL IMPACT FEE | COMMERCIAL IMPACT FEE PROCESSING | Completed | $75,237.50 in West DIstrict. 125 rooms |
| 01/05/2007 | HEATHER THRALL | ZONING | REVIEW | Denied | Zoning will be able to review the building plans over the counter once the site plan is approved by all divisions of DSD. |
| 12/18/2006 | ROBERT SHERRY | WATER | REVIEW | Approved | |
| 12/20/2006 | DAVE MANN | FIRE | REVIEW | Denied | Please add the following automatic sprinkler criteria to the plans: 1. The hazard classification of the occupancy including any special hazards. 2. The design standard to be used. 3. The availability and adequacy of the water supply. 4. The design density and the area of operation. |
| 12/28/2006 | GERRY KOZIOL | WWM | REVIEW | Denied | needs to show location/method of connection to public sewer |
| 12/29/2006 | JASON GREEN | ENGINEERING | REVIEW | Needs Review |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 01/23/2007 | SUE REEVES | REJECT SHELF | Completed |
| 01/23/2007 | SUE REEVES | OUT TO CUSTOMER | Completed |