Permit Number: T06CM03790
Parcel: 133231880

Review Status: Completed

Review Details: RESUBMITTAL - SITE ALL

Permit Number - T06CM03790
Review Name: RESUBMITTAL - SITE ALL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
11/13/2006 DAVE MANN FIRE REVIEW Approved
11/15/2006 STEVE SHIELDS ZONING REVIEW Denied DSD TRANSMITTAL

FROM: Steve Shields
Lead Planner

PROJECT: FRY'S GAS STATION ADDITION -
7770 E. Speedway Blvd.
T06CM03790
Site Plan (2nd Review)

TRANSMITTAL DATE: November 16, 2006

COMMENTS: Please resubmit revised drawings along with redlines and a response letter, which states how all Zoning Review Section comments regarding the Land Use Code and Development Standards were addressed.


1. This plan has been reviewed for compliance with development standards 2-02 site content and specifications. Additional review for compliance with development standards, 2-08, 2-09, 3-01, and 3-05 has been made. This plan has also been reviewed for compliance with development criteria as listed in the LUC for development designator "28", Retail Trade Use Group, General Merchandise Sales, subject to Sec. 3.5.9.2.C

2. The Site Plan (SP) is approved conditionally as submitted. Please include a response letter to the comments along with the corrected copies of the SP with your next submittal. An over the counter review may be used once the following comments have been addressed as long as all other agencies have approved the site plan.

3. The pedestrian circulation/accessible route, which runs from the former Los Betos pad area to the sidewalk along Speedway, presents an unsafe condition. This pedestrian circulation/accessible route needs to be relocated. See the attached redline for recommendation.

4. Ensure all changes made to this site plan are include on the site plan under review T06CM03381.

If you have any questions about this transmittal, please contact me at Steve.Shields@tucsonaz.gov or (520) 791-5608 ext. 1180.


C:\planning\site\t06cm03790-2nd.doc

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised site plan and additional requested documents
11/16/2006 STEVE SHIELDS ZONING HC SITE REVIEW Denied See Zoning Comments
11/21/2006 ANDREW CONNOR LANDSCAPE REVIEW Denied 1. Street landscape borders shall be located entirely on site, except that, if approved by the City Engineer or designee. On streets designated as Major Streets and Routes (MS&R), the street landscape border is measured from the MS&R right-of-way line as determined by LUC 2.8.3.4. Include property and ROW lines on the landscape plan.

2. A 30" continuous screen along street frontages for vehicle use area must be provided per LUC Table 3.7.2-I. Identify screening element.

3. Indicate square footage of all landscaped areas and calculation of the percentage of vegetative coverage per DS 2-07.2.2.2.g

4. The spacing of trees must be adjusted to prevent conflict with utilities and easements per DS 2-06.3.5.D. Verify if tree placement is appropriate adjacent to electrical transformer indicated in Key Note # 24 on the Site Plan.

5. Additional comments may apply.
11/22/2006 ANDREW CONNOR NPPO REVIEW Approved
12/21/2006 PAUL MACHADO ENGINEERING REVIEW Denied To: Tait and Associates DATE: December 29, 2006
Architects
Mesa, Arizona 85202

SUBJECT: 7770 E. Speedway Blvd.
Site plan T06CM003790, Grading plan
T06BU01650 (Second Review)
T14S, R15E, Section 08

RESUBMITTAL REQUIRED: Site Plan, Grading Plan and Drainage Statement.

The Site Plan (SP), Grading Plan (GP) and Drainage Statement (DS) cannot be approved as submitted. Please address the following review comments prior to the next submittal.

Site Plan, Grading Plan:

1. Please include a response letter to the comments along with the corrected copies of the SP. A detailed response letter is required, "See site plan" is too vague.
2. The SP and GP cannot be approved prior to the site plan (T06CM03381) that is currently under review.
3. As per the Federal ADA requirements, all wheel chair ramps shall have the truncated domes instead of the standard grooves that are shown on COT SD 207. Aside from the Truncated Domes, all wheel chair ramps shall be constructed in accordance with COT SD 207. Call out a COT standard detail or show a detail of the H/C ramp on the plans.
4. There shall be no obstructions in the SVT this includes any parking spaces per D.S. 3-01.5.0.
5. Please list estimated cut & fill quantities per D.S. 2-02.2.1.17. Per previous comment.
6. Edit general note no. 29 to "All work shall conform to City of Tucson Development Standard 11-01.0 Excavation and Grading".
7. Please provide existing topographic contours at intervals not exceeding two (2) feet and/or spot elevations as pertinent and Bench Mark based on City of Tucson Datum, including City Field Book and page number per D.S. 2-02.2.1.23. Call out the Bench Mark on the plans.
8. Show Site plan (T06CM03790) and Grading plan (T06BU01650) number on all sheets per D.S. 2-02.2.1.29. Per previous comment.
9. Show on the plans where the water harvesting techniques will be utilized with drainage arrows, grades and depressed curbs.
10. Show refuse container location, size, and access thereto fully dimensioned per D.S. 2-02.2.1.32 and D.S. 6-01.0. Per previous comment.
11. Please show a typical cross section of the P.A.A.L. or call out the percentage of slopes. Call out the GB at the D/W, if applicable. Per previous comment.
12. Please show the proposed roof drainage patterns, 100% of the 10-year flow must be conveyed under the sidewalks including any other site drainage as well. Please provide supporting calculations to demonstrate compliance with D.S. 3-01.4.4. If the location(s) of the roof scuppers have not yet been decided, a general note indicating sidewalk scuppers will be used when the roof scuppers locations have been designed and located will suffice. Per previous comment.
13. Submit 4 copies of the grading plan upon re-submittal.

Drainage Statement:
1. The DS has been conditionally accepted.
2. Generate drainage exhibits into the DS with pockets that show where and how the water harvesting techniques will be utilized.

If you have any questions, I can be reached at 791-5550 x1193 or Paul.Machado@tucsonaz.gov
Paul P. Machado
Senior Engineering Associate
City of Tucson/Development Services Department
201 N. Stone Avenue
P.O. Box 27210
Tucson, Arizona 85726-7210
(520) 791-5550 x1193 office
(520) 879-8010 fax
C:/7770 E. Speedway Blvd. Site&Grad 2

Final Status

Task End Date Reviewer's Name Type of Review Description
01/08/2007 GERARDO BONILLA OUT TO CUSTOMER Completed
01/08/2007 SUE REEVES REJECT SHELF Completed