Permit Number: T06CM02713
Parcel: 136313180

Review Status: Completed

Review Details: POST 3RD PARTY REVIEW

Permit Number - T06CM02713
Review Name: POST 3RD PARTY REVIEW
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
07/14/2006 GERRY KOZIOL WWM REVIEW Denied 1.CAR WASH @ QUIK MART- BUILDING #2
2.NEEDS WW/IWC REVIEW- TOM TOMCHAK 579-5771.
3. NEEDS MANHOLE TAP PERMIT(8TH FLOOR REVIEW-5TH FLOOR PERMIT)
07/14/2006 ROBERT SHERRY WATER REVIEW Approved
07/17/2006 DAVE MANN FIRE REVIEW Approved
07/18/2006 BETH GRANT COMMERCIAL IMPACT FEE COMMERCIAL IMPACT FEE PROCESSING Passed
07/19/2006 RBABBIT1 LANDFILL REVIEW Approved
07/26/2006 SUZANNE BOHNET ENGINEERING REVIEW Denied Building plans cannot be approved until the Development Plan is approved AND stamped as a Site Plan, approved by Zoning, Landscape, Engineering and Fire review sections.
08/30/2006 STEVE SHIELDS ZONING REVIEW Denied DSD TRANSMITTAL

FROM: Steve Shields
Lead Planner

PROJECT: Quick Mart - Irvington Road & Houghton Road
T06CM02713
Building Plan (1st Review)

TRANSMITTAL DATE: August 30, 2006

1. The building plan has been reviewed by Zoning Review Section but cannot approve the plan until it has been approved by the Engineering, and Landscape Review Sections and until all zoning comments or concerns have been addressed.

2. Zoning could not verify that the building plan was in compliance with the approved site plan. Please submit two copies of the approved and stamped site, landscape, and NPPO plans with the next grading plan submittal.

3. Zoning will re-review the building plan on the next submittal to insure compliance with the approved and stamped site plan. Additional comments may be forthcoming.

If you have any questions about this transmittal, please call Steve Shields,
(520) 791-5608 ext. 1180.

C:\planning\grading\t06cm02713.doc

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised site plan and additional requested documents

Final Status

Task End Date Reviewer's Name Type of Review Description
12/22/2006 FSANCHE1 OUT TO CUSTOMER Completed