Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL
Permit Number - T06CM01797
Review Name: RESUBMITTAL
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 08/31/2006 | ROBERT SHERRY | WATER | REVIEW | Approved | |
| 09/01/2006 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | 1. Revise the design of the pressure regulator installation to delete the non-valved bypass. Reference Section 608.2, UPC 2003. 2. Provide a shut off valve for the building water service 3. Provide an upper terminal cleanout for P2 located in the east restroom. Reference Section 707.4, UPC 2003. 4. The revised stack & riser diagrams show only a single 2" VTR. Provide additional venting capacity per Section 904.1, UPC 2003. (Note also that the revised design for the future restrooms will not allow the future lavatories to be wet vented through the water closet vents. See Table 10-1, UPC 2003.) 5. Coordinate the roof drain and overflow drain, as shown in detail 9/A6.0, with the roof drains and overflow drains that are specified on sheet P1.0. 6. Clarify how the roof overflow drains are to be terminated. Reference Section 103.2.3, UPC 2003. 7. Show the sizes of the building water meter and reduced pressure backflow preventor. Reference Section 103.2.3, UPC 2003. |
| 09/01/2006 | TERRY STEVENS | ZONING | REVIEW | Denied | 9-1-06 Development Services Department Zoning Review Section Terry Stevens Lead Planner Comments: 1. Zoning has reviewed the building plans but cannot approve them at this time. Zoning will re-review and approve the building plans on the next submittal providing the stamped and approved site plans are included with the building plan package. 2. Two copies of the approved and stamped site plan, landscape and NPPO plans must be included with building plans. |
| 09/01/2006 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Approved | |
| 09/11/2006 | LINDA BUCZYNSKI | ELECTRICAL-COMMERCIAL | REVIEW | Approved | |
| 09/13/2006 | PATRICIA GILBERT | ENGINEERING | REVIEW | Denied | An approved site plan is required prior to building plan approval. |
| 09/22/2006 | GERRY KOZIOL | WWM | REVIEW | Denied | needs to show location/method of connection to public sewer. |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 09/28/2006 | CINDY AGUILAR | OUT TO CUSTOMER | Completed |
| 09/28/2006 | SUE REEVES | REJECT SHELF | Completed |