Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
11/22/2006 | ANDREW CONNOR | NPPO | REVIEW | Denied | 1. Submit a copy of the landscape and native plant preservation plans for reference. The grading application will be reviewed for compliance only when the documents are included in the submittal. 2. The grading plan has been reviewed but cannot approve it until all Engineering comments or concerns have been addressed. |
12/12/2006 | MICHAEL ST. PAUL | ZONING | REVIEW | Denied | December 12, 2006 Development Services Department Zoning Review Section Michael St.Paul Planning Technician T06BU02625 Grading Stockpile Plan for S06-117 Comments: 1. The grading plan has been reviewed by Zoning Review Section but cannot approve the plan until it has been approved by the Engineering, and Landscape Review Sections and until all zoning comments or concerns have been addressed. 2. Zoning could not verify that the grading plan was in compliance with the approved grading plan and tentative plat. Please submit one copy of the CDRC approved and stamped tentative plat, landscape, and NPPO plans with the next grading plan submittal. 3. Zoning will re-review the grading plan on the next submittal to ensure compliance with the CDRC approved and stamped tentative plat. Additional comments may be forthcoming. |
12/19/2006 | PAUL MACHADO | ENGINEERING | REVIEW | Denied | To:Stantec Consulting Engineers, DATE: December 19, 2006 Ryan Stuki, P.E. 201 N. Bonita Avenue Tucson, Arizona 85711 SUBJECT: Wingate Lot 3, 8903 E. Linderbrook Dr. Stockpile Plan T06BU02625 (First Review) T14S, R15E, Section 34 RESUBMITTAL REQUIRED: Stockpile Plan, Drainage Report and SWPPP The Stockpile Plan (SP), Drainage Statement (DS) and Stormwater Pollution Prevention Plan (SWPPP) cannot be approved as submitted. Please address the following review comments prior to the next submittal. Stockpile Plan: 1. Please include a response letter to the comments along with the corrected copies of the SP. 2. Stockpile plan clearly marked "STOCKPILE PLAN ONLY". 3. There appears to be a significant area proposed to be disturbed for the stockpile. Only the necessary area will be approved for this temporary stockpile permit. Revise limits so that only the following areas are disturbed: · The entrance area with limited width dimensioned on plan view. · Stockpile area with slope runout. · Limited vehicle access area around the perimeter of the stockpile, also dimensioned on the plan. 4. There appears to be a discrepancy of name of the subdivision and block between the SP, DS and SWPPP. Revise as required. 5. Remove reference box to the type 2 grading permit for this project on sheet 1. 6. Remove "Accepted" line by the City of Tucson on the cover sheet. 7. Replace general note 25 with "All work shall conform to the City of Tucson Development Standards Chapter 11-01.0, Excavation and Grading". 8. List administrative address/site address on plans. 9. Complete Stockpile plan number (T06BU02625) on the cover sheet. 10. Show cross section with transverse and longitudinal slopes. 11. Delineate 100-year W.S.E.L., Floodplain and erosion hazard setback. 12. Call out all slopes and stabilization material (concrete, riprap, gabbions or vegetation) if applicable. Drainage Statement: 1. Please include a response letter to the comments along with the corrected copies of the DS. 2. There appears to be a significant area proposed to be disturbed for the stockpile. Only the necessary area will be approved for this temporary stockpile permit. Revise DS to reflect the necessary changes needed on the SP. · The entrance area with limited width dimensioned on plan view. · Stockpile area with slope runout. · Limited vehicle access area around the perimeter of the stockpile, also dimensioned on the plan. 4. Delineate 100-year W.S.E.L., Floodplain and erosion hazard setback. 5. There appears to be a discrepancy of name of the subdivision and block between the SP, DS and SWPPP. Revise as required. 6. Due to required revisions on the SP, further comments to the DS may be necessary upon re-submittal. 7. Show the project address on the cover of the Drainage Statement. Stormwater pollution prevention plan: 1. The SWPPP will need to be updated to reflect all the required changes to the SP. 2. Due to required revisions on the SP, further comments to the SWPPP may be necessary upon re-submittal. If you have any questions, I can be reached at 791-5550 x1193 or Paul.Machado@tucsonaz.gov Paul P. Machado Senior Engineering Associate City of Tucson/Development Services Department 201 N. Stone Avenue P.O. Box 27210 Tucson, Arizona 85726-7210 (520) 791-5550 x1193 office (520) 879-8010 fax C:/8903 E. Linderbrook Dr. Stockpile |
Final Status
Task End Date | Reviewer's Name | Type of Review | Description |
---|---|---|---|
12/28/2006 | GERARDO BONILLA | OUT TO CUSTOMER | Completed |
12/28/2006 | SUE REEVES | REJECT SHELF | Completed |