Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Number: T06BU01659
Parcel: 140410530

Review Status: Completed

Review Details: RESUBMITTAL - GRADING ALL

Permit Number - T06BU01659
Review Name: RESUBMITTAL - GRADING ALL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
11/14/2006 HEATHER THRALL ZONING REVIEW Denied zoning will review this plan further at the counter once engineering has approved it and the site plan has been approved. Please bring copies of the approved site plan with the submittal of this grading plan.
11/27/2006 JASON GREEN ENGINEERING REVIEW Denied DATE: November 27, 2006
SUBJECT: 6575 S Country Club Road- 2nd Engineering Review of Site Plan and Grading Plan
TO: Metro Permits Express
LOCATION: T15S R14E Sec16, Ward 5
REVIEWERS: Jason Green, CFM
ACTIVITY: T06CM03798 (site plan) and T06BU01659 (grading plan)


SUMMARY: Engineering Division of Development Services Department has received and reviewed the re-submitted site plan (T06CM03798), and grading plan (T06BU01659), drainage report (prepared by The WLB Group, Inc.), and Geotechnical Soils Investigation for the above referenced property. Engineering Division does not recommend approval of the site plan or grading permit application at this time. The drainage report was reviewed for site plan and grading plan purposes only. The following items need to be addressed:


SITE PLAN COMMENTS:

1) DS Sec.3-01: Provide the standard right-of-way widths and curb knuckle design per Figure 22 and list the required information on the Offsite Public Street Plan for review:
I. Provide the dimensions for the standard knuckle radii.
II. Provide the tangent lines at all intersect points per detail.
III. Provide the degree and bearing for all other lines as shown in the standard detail for knuckle design.
IV. Show street monuments per the standard detail.

2) DS Sec.2-02.2.1.A.12: Revise the continuous pedestrian circulation path from Country Club Road so that is fully connects to the Porte Corchere area.

3) DS Sec.2-02.2.1.A.12: Provide handicap access ramps at the sidewalk locations that cross the ingress/egress located off of Bonney Road and the maneuvering area for the trash collection area. Truncated domes are required for all proposed handicap access ramps.

4) DS Sec.2-02.2.1.A.14: Label and show on the site plan the required maneuvering area for all loading zones that are shown on the development plan. Refer to AASHTO for the national standards for turning radii.

5) DS Sec.2-02.2.1.A.15: Provide the 100-year floodplain limits for the proposed channel and the 100-year ponding limits for the proposed 14-EF-1 grate inlets and modified trench drain in the cul-de-sac of Bonney Ave. Provide this information in plan view and on detail 7/4, Sheet 4 of 6 . Ponding limits within the right-of-way for Bonney Ave must be checked to assure all weather access.

6) DS Sec.2-02.2.1.A.19: Proposed improvements can not be located within the future right-of-way of Country Club Road. Revise the site plan and grading plan to show that all improvements are located outside of the future right-of-way and that all improvements are located on the subject parcel.

7) DS Sec.11-01.4.1.C.6: Revise the building location so that is meets the minimum recommended setback of 30-feet from the proposed channel. The building location must meet the minimum recommendations included in the geotechnical report addendum that was prepared October 24, 2006.

8) DS Sec.11-01.9: Revise the site plan and grading plan to provide the required 2-feet setback from all property boundaries to the proposed limits of grading, fill slopes, and associated erosion protection. The plan view on the site and grading plan shows that the limits of grading, top of fill slope for proposed basins, and the erosion control structures encroach into the required 2-feet setback and the right-of-way width. Provide sufficient room to allow for the 2-feet setback from property lines to top of fill slopes and associated erosion protection.

9) DS Sec.3-01.3.3.A: Provide on the site plan the required 6-foot wide sidewalk with curb along the street frontage of Country Club Road. Per the adopted Mayor and Counsel policy all sidewalks along MS&R right-of-ways for arterial and collector streets require 6-foot wide sidewalks. Label the sidewalk to be constructed as 6-foot.

10) DS Sec.3-01.3.3.A: Revise the site plan so that the future sidewalk and access ramps do not encroach into the proposed basin. The plan view shows the future handicap access ramp within the proposed basin and across the proposed weir structure.

11) DS Sec.3-01.3.3.A: Revise the site plan so that the proposed 6-foot wide sidewalk along Valencia Road connects to the shown handicap access ramps. All improvements must tie into and function for pedestrian circulation.

12) DS Sec.2-02.2.1.A.32: Label and show the maneuverability for refuse vehicles in plan view at the proposed refuse container location.


GRADING PLAN COMMENTS:

13) DS Sec.11-01.4.1.C.4: Revise the proposed 14 EF-1 grate inlets to provide for a more traversable alignment for bicycle traffic along Bonney Road. Revise the storm drains so that they are perpendicular to the alignment of the revised roadway. Provide a revised detail for the 7'x3' wide modified trench drains that are proposed in the cul-de-sac.

14) Provide a scupper at the low point in the street adjacent to the channel inlet for flows that are not captured by the proposed 14 EF-1 grate system.

15) DS Sec.11-01: Revise Grading Note #16 on Sheet 6 of 6 to include "Development Standard 11-01.0 (excavation and grading requirements)."

16) DS Sec.11-01.4.1.C.4: Revise details on the grading plan for all rock riprap areas to call out whether the riprap is grouted, hand placed or dumped.

17) DS Sec.11-01.4.1.C.6: Provide on the grading plans all recommendations that are in the submitted geotechnical report. Slopes in the range of 3:1 to 1.5:1 need to be stabilized with a minimum 6-inch diameter riprap. Revise all details for the proposed basins to show that the recommendations have been addressed.

18) DS Sec.11-01.4.1.C.6: Provide a detail for the 1:1 slope that is shown at both bends of the proposed channel to allow for freeboard for super-elevated flows. Recommendations of the soils engineering report must be incorporated within the detail for slope stability and erosion protection.

19) DS Sec.11-01.4.1.F: Provide typical lot grading details, show minimum side and rear setbacks, and building setbacks to the detention and retention basins and swales per geotechnical report. Provide detailed cross sections for each perimeter, fully labeled and dimensioned. These details were not located in plan view or on the detail sheets provided.


DRAINAGE REPORT:

20) Provide a signed and notarized 404 Compliance Statement that is included on Page 7 of the Drainage Report.

21) DS Sec.2-02.2.1.A.15: Clarify or revise the drainage report for the parcel showing that the developed discharge for the 2, 10, and 100-year flow events are less than the existing corresponding discharge values with a 15 % reduction. The Basin Summation for the overall onsite and offsite flows does not show a 15% decrease in discharge for developed conditions. The drainage report must meet the minimum standards for development outlined in the Stormwater Detention/Retention Manual.


STORMWATER POLLUTION PREVENTION PLAN: The SWPPP does not meet the minimum requirements of the AzPDES Construction General Permit (CGP). Revise the SWPPP according to these comments:

1) Revise the SWPPP Report so that the Sections listed in the Table of Contents are in chronological order and clearly labeled for easier use in the field.

2) CGP Part IV.2.d: Revise Page 2, Section 1.6 to state the actual increase in impervious cover.

3) CGP Part IV.C.2.e: The general location map that was provided under separate cover needs to be bound into the report in Appendix A.

4) CGP Part IV.C.3.c: Revise the SWPPP sheet to provide for straw bales at the inlet to all culverts. Provide waddles, or equivalent, around the proposed 14 EF-1 grate located in the right-of-way and at the inlet to all curb openings around the proposed basin. Or provide a statement of which basins are been used as sediment traps during the construction of the proposed project.

5) CGP Part IV.C.4: Provide on the SWPPP Exhibit the name of the nearest receiving watercourse that the stormwater is discharged into downstream.

6) CGP Part IV.D.5.a.i: Describe the location, size and retention capacity of all 4 retention/detention basins and the areas that drain into them.

7) CGP Part IV.D.5.a.iii: Provide a statement and describe how and where sediment basins or sediment traps are used for areas <10 disturbed acres, or storage for a 2-year, 24 hour storm per disturbed acre drained.


GENERAL COMMENTS:

Please provide a revised site plan, revised grading plan, revised drainage report, and a revised SWPP that address the comments provided above. Include a comprehensive response letter addressing in detail responses to all of the above comments.

Further comments may be generated upon resubmittal of the site plan, grading plan, drainage report, and SWPPP reviews. Site plan must be approved prior to grading plan approval.

If you have any questions, or to schedule an appointment, I can be reached at 791-5550, extension 1189.



Jason Green, CFM
Senior Engineer Associate
Engineering Division
Development Services
11/28/2006 ANDREW CONNOR NPPO REVIEW Denied Submit a copy of the approved site plan including landscape and native plant preservation plans for reference. The grading application will be reviewed for compliance only when the approved documents are included in the submittal. Revise grading plans as necessary to comply with the approved site plan.

Final Status

Task End Date Reviewer's Name Type of Review Description
11/30/2006 BETH GRANT OUT TO CUSTOMER Completed
11/30/2006 SUE REEVES REJECT SHELF Completed