Permit Number: T06BU00947
Parcel: 13819037A

Review Status: Completed

Review Details: RESUBMITTAL - GRADING

Permit Number - T06BU00947
Review Name: RESUBMITTAL - GRADING
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
03/05/2007 ANDREW CONNOR NPPO REVIEW Approv-Cond
03/06/2007 PATRICIA GILBERT ENGINEERING REVIEW Denied DATE: March 5, 2007
ACTIVITY NUMBER: T06BU00947
PROJECT NAME: Los Reales Branch
PROJECT ADDRESS: 369-371 West Valencia Road
PROJECT REVIEWER: Patricia Gilbert

The following items must be revised or added to the grading plan. Please include a response letter with the next submittal that states how all comments have been addressed.

The next review of the site plan can be an over the counter review. Please contact me to schedule a time when we can meet. When we meet open a new workflow in Permits Plus and communicate to the Customer Service Representative at the counter, that the review will be an "over the counter review."


RESUBMITTAL REQUIRED: FOUR COPIES OF THE GRADING PLAN AND SWPPP.

1. A copy of the stamped approved Site Plan must be included with the Grading Plan submittal.

2. The Site Plan is currently in review. Any changes made to the Site Plan must be reflected on the Grading Plan. The Site Plan and Grading Plan must match.

3. The revised water surface elevations (WSE) found on figure 4, in the drainage report do not match the WSE shown on the grading plan. Revise the grading plan to show the revised WSE found in the drainage report.

SWPPP COMMENTS

1. The certification statement needs to be signed prior to approval of the SWPPP. This assures the City of Tucson prior to issuance of a grading permit that there is a designated responsible party for the SWPPP.

The above comment is from the previous review and has not been addressed. It is acknowledged the response to this comment is the contractor will sign upon picking up the permit. However at minimum the owner should sign the certification statement prior to approval of the SWPPP.

2. Provide signatures on the provided NOIs. Each operator is responsible for submitting a completed NOI to ADEQ and a copy to the City of Tucson. Provide copies of the signed NOIs in the narrative. (Part IV.F)

Final Status

Task End Date Reviewer's Name Type of Review Description
03/13/2007 DELMA ROBEY OUT TO CUSTOMER Completed
03/13/2007 SUE REEVES REJECT SHELF Completed