Permit Number: T06BU00725
Parcel: 12214018A

Review Status: Completed

Review Details: GRADING

Permit Number - T06BU00725
Review Name: GRADING
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
04/07/2006 ANDREW CONNOR NPPO REVIEW Denied Site plan approval is necessary to continue review.
04/13/2006 SUZANNE BOHNET ENGINEERING REVIEW Denied To: George Holguin / ADC West
DATE: April 18, 2006
FROM: Suzanne Bohnet
Engineering Division

SUBJECT: 3120 E. Adams St., Bldg. 2
New Apartments
Site plan T06CM00236 (First Review)
Grading plan T06BU00725 (First Review)
T14S, R14E, Section 04

RESUBMITTAL REQUIRED: Site Plan and Grading Plan.

The Site Plan (SP) and Grading Plan (GP) cannot be approved as submitted. Please include a response letter to the comments along with the corrected copies of the SP with your next submittal.

Site Plan:
1. Please include the GP from the Drainage Statement as part of the sheets with the SP or include the information from the GP on the same sheet as the SP, labeling as "Site/Grading Plan".
2. Please provide the basis of bearings for the lot and the vertical datum used for elevations.
3. The sidewalk along the Right-of-Way (ROW) is required to be a minimum of 5 feet wide rather than the proposed 4 feet. Please modify.
4. The onsite pedestrian circulation paths require a minimum width of 4 feet, not 3 feet. Please modify.
5. It appears that drainage from the roof of the proposed structure will concentrate flow towards the proposed sidewalks located north of the proposed structure. 100% of the 10-year flow must be conveyed under the sidewalks via a scupper(s). Please provide supporting calculations to demonstrate compliance with DS 3-01.4.4.
6. Please show truncated domes on the sidewalk ramps and provide a detail for them.
7. Please list the estimated cut and fill quantities in cubic yards.
8. Please include the drainage patterns and finished grade spot elevations.
9. Please provide the dimensions from the street monument lines to the existing/proposed curbs, sidewalks, driveways and utility lines.
10. Please provide a centralized onsite refuse storage, collection and pickup area with service access per DS 6-01.2.2A. Include a detail of the dumpster enclosure.
11. If onsite refuse collection is not feasible, please contact John Clark for options. Be advised a Development Services Modification Request (DSMR) will be required in this event.
12. If onsite refuse collection is provided, then an 18-foot curb return radius is required for the driveway along Adams St. per DS 3-01.0 Figure 6.

Grading Plan:
1. If you prefer to have separate sheets for the SP and the GP, please ensure the GP is clearly marked "Grading Plan". Be sure to include the comments below on the SP if a combined "Site/Grading Plan" sheet is preferred.
2. Water harvesting techniques shall be incorporated into the development by conveying rooftop drainage to designated water harvesting areas. Please address how water-harvesting techniques will be incorporated into the development. Refer to the newly adopted City of Tucson Water Harvesting Guidance Manual for design considerations. Copies of the above-referenced manual can be obtained from the Engineering Counter. Also, please add the following note: "Depress all landscaped areas a maximum of 6" for water harvesting".
3. A permit of a private improvement agreement will be necessary for any work performed within the ROW. Contact Permits and Codes at (520) 791-5100 for permit information.

If you have any questions, I can be reached at 791-5550 x1188.
Suzanne Bohnet, Engineer Associate
Suzanne.Bohnet@tucsonaz.gov
04/29/2006 DAVID RIVERA ZONING REVIEW Denied 04/29/06

Development Services Department
Zoning Review Section

David Rivera
Principal Planner

Comments:

1. The grading plan has been reviewed by Zoning Review Section but cannot approve the plan until it has been approved by the Engineering, and Landscape Review Sections and until all zoning comments or concerns have been addressed.

2. Zoning could not verify that the grading plan was in compliance with the approved site plan. Please submit two copies of the approved and stamped site, landscape, and NPPO plans with the next grading plan submittal.

3. Zoning will re-review the grading plan on the next submittal to ensure compliance with the approved and stamped site plan. Additional comments may be forthcoming.