Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Number: T06BU00572
Parcel: 10704006C

Address:
1564 W GRANT RD

Review Status: Completed

Review Details: RESUBMITTAL - GRADING ALL

Permit Number - T06BU00572
Review Name: RESUBMITTAL - GRADING ALL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
01/04/2007 JASON GREEN ENGINEERING REVIEW Approved DATE: January 4, 2007
SUBJECT: 1564 W Grant Road- 3rd Engineering Review of Site Plan andGrading Plan
TO: Metro Permits Express
LOCATION: T13S R13E Sec34, Ward 1
REVIEWERS: Jason Green, CFM
ACTIVITY: T06CM01697 (site plan) and T06BU00572 (grading plan)


SUMMARY: Engineering Division of Development Services Department has received and reviewed the revised site plan (T06CM01697), grading plan, drainage report (prepared by Grenier Engineering, Inc.), geotechnical report addendum (prepared by Western Technologies, Inc), and Stormwater Prevention Pollution Plan (SWPPP), for the above referenced property. Engineering Division recommends approval of the site plan and grading plan at this time.

ยท Field clarification may be needed for the temporary control measures that must be provided around the concrete, stucco and paint washout area. Refer to the Caltran Storm Water Quality Handbook submitted within the SWPPP for wash out area requirements.


If you have any questions I can be reached at 791-5550, extension 1189.



Jason Green, CFM
Senior Engineer Associate
Engineering Division
Development Services
12/14/2006 STEVE SHIELDS ZONING REVIEW Denied DSD TRANSMITTAL

FROM: Steve Shields
Lead Planner

PROJECT: Holiday Inn Express - 1564 W. Grant Road
T06BU00572
Grading Plan (3rd Review)

TRANSMITTAL DATE: December 14, 2006

1. The grading plan has been reviewed by Zoning Review Section but cannot approve the plan until it has been approved by the Engineering, and Landscape Review Sections and until all zoning comments or concerns have been addressed.

2. Zoning could not verify that the grading plan was in compliance with the approved site plan. Please submit two copies of the approved and stamped site, landscape, and NPPO plans with the next grading plan submittal.

3. Zoning will re-review the grading plan on the next submittal to insure compliance with the approved and stamped site plan. Additional comments may be forthcoming.

If you have any questions about this transmittal, please call Steve Shields,
(520) 791-5608 ext. 1180.

C:\planning\grading\t06bu00572-3rd.doc

RESUBMITTAL OF THE FOLLOWING IS REQUIRED: Revised site plan and additional requested documents
12/26/2006 ANDREW CONNOR NPPO REVIEW Approv-Cond

Final Status

Task End Date Reviewer's Name Type of Review Description
01/12/2007 GERARDO BONILLA OUT TO CUSTOMER Completed
01/12/2007 SUE REEVES REJECT SHELF Completed