Plan Review Detail
Review Status: Completed
Review Details: PIA RESUBMITTAL
Plan Number - T05PI00028
Review Name: PIA RESUBMITTAL
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 03/08/2006 | Estevan Tineo | DOT ENGINEERING | REVIEW | Denied | 1. Previous comment No.9 not addressed. 2. Provide the previous red-lines for review and reference. 3. Previous plans and, I beleive floodplain use permit, idicated pipe mitered to conform to slope? Please explain projecting pipe and revise accrodingly. 4. The plan must indicate pipe to maintained by HOA. |
| 03/09/2006 | GARY WITTWER | DOT LANDSCAPE | REVIEW | Denied | See last reveiw comments. Need to address NPPO in Alamo Wash. |
| 03/22/2006 | THAUSER1 | CONSTRUCTION ESTIMATE | REVIEW | Needs Review | |
| 03/22/2006 | THAUSER1 | ENGINEERING | REVIEW | Needs Review | |
| 03/22/2006 | THAUSER1 | UTILITY CLEARANCES | COT STREETS DIVISION | Needs Review | SUBMIT UTILITY CLEARANCE LETTERS |
| 03/22/2006 | THAUSER1 | UTILITY CLEARANCES | COT WATER NEW DEVELOPMENT | Needs Review | SUBMIT UTILITY CLEARANCE LETTERS |
| 03/22/2006 | THAUSER1 | UTILITY CLEARANCES | PC WASTEWATER MGMT | Needs Review | SUBMIT UTILITY CLEARANCE LETTERS |
| 03/22/2006 | THAUSER1 | UTILITY CLEARANCES | QUEST COMMUNICATION | Needs Review | SUBMIT UTILITY CLEARANCE LETTERS |
| 03/22/2006 | THAUSER1 | UTILITY CLEARANCES | TUCSON ELECTRIC POWER CO | Needs Review | SUBMIT UTILITY CLEARANCE LETTERS |
| 03/22/2006 | THAUSER1 | UTILITY CLEARANCES | COX COMMUNICATION | Needs Review | SUBMIT UTILITY CLEARANCE LETTERS |
| 03/22/2006 | THAUSER1 | UTILITY CLEARANCES | SOUTHWEST GAS CORP | Needs Review | SUBMIT UTILITY CLEARANCE LETTERS |
| 03/22/2006 | THAUSER1 | UTILITY CLEARANCES | EL PASO NATURAL GAS | Needs Review | SUBMIT UTILITY CLEARANCE LETTERS |
| 03/22/2006 | THAUSER1 | UTILITY CLEARANCES | KINDER MORGAN ENERGY | Needs Review | SUBMIT UTILITY CLEARANCE LETTERS |
| 03/24/2006 | THAUSER1 | PIA COORDINATOR | CUSTOMER CALLED; PLANS @ AMBASSADOR | Completed | |
| 03/24/2006 | THAUSER1 | PIA COORDINATOR | OUT TO CUSTOMER | Completed |