Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Plan Review Detail
Review Status: Completed
Review Details: PIA REVISION
Plan Number - T05PI00002
Review Name: PIA REVISION
Review Status: Completed
Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
---|---|---|---|---|---|
03/27/2007 | Estevan Tineo | DOT ENGINEERING | REVIEW | Denied | 1. Per the Drainage Addendum 100-year flow exceeds 100-cfs, provide floodplain use permit number (from dsd) for the proposed drainage improvements. 2. Detail each type of pedestrian access ramp on this plan, this plan must stand-alone. 3. The Drainage addendum must indicate pre and post 100-year floodplain limits, the improvements must not increase existing 100-year floodplain limits. 4. The drainage addendum mentions that the proposed storm drain is to tie-into an existing storm drain. However, the report does not document if the existing storm drain has the capacity to convey the additional flow. 5. Please add the notes as attached and remove the redundant notes accordingly. 6. How will vehicles be prevented from entering the proposed drainage catch basin? Should a physical barrier be placed to mitigate vehicles from driving into to the proposed drainage sump? 7. According to the plan the proposed improvements will encroach onto private property, Will be private property be obtained and dedicated to public r/w? |
04/18/2007 | VINCE CATALANO | DOT TRAFFIC | REVIEW | Approved | |
04/23/2007 | GARY WITTWER | DOT LANDSCAPE | REVIEW | Denied | Please submit landscape and irrigation plans. |
04/23/2007 | LANCE PETERSON | DOT STREET MAINTENANCE | REVIEW | Denied | We have reviewed these plans and have the following comments: 1. Please provide a Streets and Traffic Maintenance Signature Block. 2. Will there be any landscaping in the round-about? If so, please submit the landscaping and irrigation plans to Paul Rosenboom at 4004 S. Park Avenue, Bld#2. 3. Sheet 7 - There appears to be a ponding area between points 164 and 162. 4. Will there be any deliniation to help keep traffic in the desired lanes. The medians and the round-about all have concrete header, which is flush with the existring asphalt. What will keep traffic fom driving over the headers? 5. All work in the right of way needs to be cordinated with Paul Rosenboom at 791-3154 ext 234 to prevent damage to existing landscaping and irrigation. No furhter comments. 4/23/07 |
04/24/2007 | ASHOFFS1 | PIA COORDINATOR | CUSTOMER CALLED; PLANS @ AMBASSADOR | Completed | |
04/24/2007 | ASHOFFS1 | PIA COORDINATOR | OUT TO CUSTOMER | Completed |