06/12/2006 | DALE KELCH | DOT TRAFFIC | REVIEW | Approved | I met with Josh Potter with WLB Group this morning. He was able to demonstrate for me that all of Dale Kelch's comments have been incorporated into the plans. I told him it was OK to proceed to the mylars. I also indicated it was OK to coalesce the separate striping plans sets into the rest of the plans, so there will be one submittal for on-site improvements and one submittal of the off-site improvements. The striping plans will be added as Sheets "S-1" (etc.). |
06/12/2006 | Estevan Tineo | DOT ENGINEERING | REVIEW | Approved | Based on the revised plans and my previous comments, that I reviewed this morning at a meeting with the consultant, I have no further comments on the subject plans. |
06/12/2006 | TAMI HAUSER | ENGINEERING | REVIEW | Completed | |
06/12/2006 | TAMI HAUSER | PIA COORDINATOR | CUSTOMER CALLED; PLANS @ AMBASSADOR | Completed | |
06/12/2006 | TAMI HAUSER | PIA COORDINATOR | OUT TO CUSTOMER | Completed |