Permit Review Detail
Review Status: Completed
Review Details: RESUBMITTAL - SITE ALL
Permit Number - T05OT01079
Review Name: RESUBMITTAL - SITE ALL
Review Status: Completed
| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 04/29/2005 | JIM EGAN | FIRE | REVIEW | Approved | |
| 05/12/2005 | BLANCA ESPINO | ENGINEERING | REVIEW | Denied | Site Plan 1. Please include a response letter with the next submittal that states how all comments have been addressed. 2. All lettering and dimensions shall be the equivalent of twelve (0.12") point or greater in size. The purpose of this requirement is to assure that all lettering is legible when reviewed and will maintain that legibility when reproduced and photographically reduced (microfilmed) for record-keeping purposes. D.S. 2-05.2.1.C Correct and revise all text to meet code. 3. Indicate legal property description as per the letter from Mr. Gary Wong of the Office of the Pima County Assessor. D.S. 2-02.2.1.A.2 4. Indicate project addresses. D.S. 2-02.2.1.A.3 5. Indicate location map. D.S. 2-02.2.1.A.4 6. Indicate all existing and proposed buildings and structures, including roof slope and location of downspouts and sidewalk scuppers. D.S. 2-02.2.1.A.6 Sidewalks shall be flood free for all storm discharges of up to a ten (10) year flood event. Add note, "All roof spouts will be routed under any adjacent sidewalk." D.S. 2-08.3.1 & 4.1.E 7. Indicate existing and future sight visibility triangles. D.S. 2-02.2.1.A.10 Near side is 180-feet, Far side is 110-feet. Correct and revise. 8. Indicate drainage patterns, proposed finish floor elevation(s) and finish grades. Do not obstruct offsite to onsite flows. D.S. 2-02.2.1.A.16 9. Indicate all easements of record to be graphically shown on the plan together with recording docket and page reference. D.S. 2-02.2.1.A.20 10. Indicate refuse container location, size and access. 11. Indicate the adjacent building footprint to the west. Indicate existing and proposed material to be used for the Ingress/Egress Easement. If you have any questions or would like to meet with me before your next submittal, you may contact me at 791-5640 ext.1188 or Blanca.Espino@tucsonaz.gov |
| 05/20/2005 | ANDREW CONNOR | NPPO | REVIEW | Denied | 13. Submit NPPO plan or application for exception per DS 2-15.0 |
| 05/20/2005 | ANDREW CONNOR | LANDSCAPE | REVIEW | Denied | Submit NPP plan or application for exception per DS 2-15.0 |
| 06/04/2005 | HEATHER THRALL | ZONING HC SITE | REVIEW | Passed | |
| 06/06/2005 | HEATHER THRALL | ZONING | REVIEW | Denied | DSD TRANSMITTAL FROM: Heather Thrall Senior Planner FOR: David Rivera Principal Planner PROJECT: T05OT01079 3617/3619 E. Monte Vista Drive Two new, four bedroom residences Site plan 1st Review Transmittal date: June 6, 2005 COMMENTS: Please resubmit revised drawings along with redlines and a response letter, which states how all Zoning Review Section comments regarding the Land Use Code and Development Standards were addressed. 1. Please provide square footages for both residences in the lot coverage notes on the site plan. 2. Provide a note on the site plan clarifying each building is a single family residence. 3. Please delineate the easement type, width and length on the site plan. 4. Please provide a copy of the model plan with the resubmittal, and note the city assigned model plan number (Blue162825) on the site plan. 5. The model plans associated with this project show all elevation measurements are taken from finished floor, whereas the submitted site plan takes measurements from finished grade. The difference between the finished grade and finished floor elevation is six (6) inches. The submitted site plan should be corrected to show an additional six (6) inches of height to each building wall and overall structural height. 6. Per comment 5, the height of the north exterior building wall of unit 3619 is accurately measured from grade to the top of the wall at 13 feet, 8 inches. Per the LUC, the required minimum setback of a mutli-family R-2 site abutting an R-2 zone is: the greater of ten (10) feet or ¾ of the height of the exterior building wall of the proposed structure (Sections 2.3.5.2.A.3, Designator "K", 3.2.3.1, Table C Designator "K", Designator "BB", 3.2.6.4., same zone). The submitted site plan shows a setback of ten (10) feet from the north property line to building 3619, which has a building wall height of 13 feet, 8 inches. The required minimum setback is greater than the ten (10) feet provided on the site plan, given this wall height. Please revise the site plan to meet setback requirements. The alternative is to obtain a Lot Development or Design Development Option (LDO/DDO). Please see comment 9 for details on the LDO/DDO process. 7. On the site plan, the heights of the North, South, East and West exterior building walls are listed incorrectly - per the model elevation plans and site plan building footprints provided. Please revise the site plan notes accordingly, noting comment 5 as well. 8. Please clarify the project is on Monte Vista Drive. 9. Staff noted the Lot Split project, S05-058, must be completed before this project can be approved. Please provide staff with the recorded legal descriptions and official address certificates for the lot split from parcel 3615 E. Monte Vista Drive. 10. Please provide the last city approved site plan for the adjacent property to the west on the resubmittal. These records are needed to allow review of access to the site. Please be sure to include access agreement information, notarized and recorded with the Pima County Recorder's office. 11. Per the Zoning Administrator's determination, any property requiring or providing five (5) or more parking spaces must have the parking area developed to meet commercial parking lot requirements listed in Development Standards (DS) 3-05. Per DS3-05, please add the following information on the site plan: Parking Area Access Lane (PAAL) widths, distance from the end of the carport to the PAAL, lengths and widths of all parking spaces, parking bumper details and back up spur details. Please review DS 3-05 for further information. 12. Due to the need for commercial parking lot criteria, a pedestrian path must be provided from Monte Vista to all residences, 3615 (your other recent project), 3617 and 3619. The pedestrian path must meet requirements of DS 2-08. 13. These review comments are not official referral comments to the LDO/DDO process. Should you have any questions on this review, or wish to obtain a referral to the LDO/DDO process, please contact me via email at Heather.Thrall@tucsonaz.gov or at 791-4541x1156 to make an office appointment. If you have any questions about this transmittal, please call (520) 791-5608. |
Final Status
| Task End Date | Reviewer's Name | Type of Review | Description |
|---|---|---|---|
| 06/09/2005 | JMORALE1 | OUT TO CUSTOMER | Completed |
| 06/09/2005 | SUE REEVES | REJECT SHELF | Completed |