Permit Number: T05OT00211
Parcel: 11450001A

Review Status: Completed

Review Details: RESUBMITTAL - SITE ALL

Permit Number - T05OT00211
Review Name: RESUBMITTAL - SITE ALL
Review Status: Completed
Review Date Reviewer's Name Type of Review Description Status Comments
08/20/2005 JIM EGAN FIRE REVIEW Denied
08/29/2005 ANDREW CONNOR NPPO REVIEW Denied The site plan, landscape and NPP plans must show identical site layout to avoid conflict between the plans per DS 2-02.2.1.C. Revise landscape and NPP plans as necessary to indicate the nature and extent of the work proposed, and eliminate any mitigated plants within WASH study area if no disturbance is to occur.

2. Applications filed under SCZ Overlay procedure require review and decision by the development services department (DSD) director or designee certifying the implementation of all applicable LUC requirements of the SCZ zone. Include SCZ approval documentation with re-submittal.
08/29/2005 ANDREW CONNOR LANDSCAPE REVIEW Denied 1. The site plan, landscape and NPP plans must show identical site layout to avoid conflict between the plans per DS 2-02.2.1.C. Revise landscape and NPP plans as necessary to indicate the nature and extent of the work proposed, and eliminate any mitigated plants within WASH study area if no disturbance is to occur.

2. Applications filed under SCZ Overlay procedure require review and decision by the development services department (DSD) director or designee certifying the implementation of all applicable LUC requirements of the SCZ zone. Include SCZ approval documentation with re-submittal.
08/29/2005 DAN CASTRO ZONING REVIEW Denied COMMENTS: Please resubmit revised drawings along with redlines and a response letter, which states how all Zoning Review Section comments regarding the Land Use Code and Development Standards were addressed.

1. Site plan may not be approved prior to SCZ approval. SCZ plan is currently under a twenty-day public comment period, which expires on August 31, 2005 and a fourteen day appeal period then commences. Once the fourteen-day appeal period expires successfully, Zoning Review may then stamp and approve the site plan.

2. Review of this plan by the Zoning Review Section may be done over the counter. Please contact Dan Castro to set an appointment.

If you have any questions about this transmittal, please call Dan Castro, (520) 791-5608 ext. 1180. An appointment is required to discuss these comments in person.
09/15/2005 PAUL MACHADO ENGINEERING REVIEW Denied To: Benjamin Cole DATE: September 16, 2005
Architect
7065 N. Oracle Rd.
Tucson, Arizona 85704

SUBJECT: 8526 E Tanque Verde Rd., Bandelero Ranch
Site plan T05CM00211 (Fourth Review)
Floodplain Use Permit T05OT00218 (Fourth Review)
T13S, R15E, Section 33
RESUBMITTAL REQUIRED: Site plan and Drainage Report
Site Plan:
1. Per the your response comments, all buildings were removed form the WASH mitigation area, hence the changes done on the site plan for this submittal. However, portions of the buildings were not removed from the WASH mitigation area and will be required to be completely removed if the resource area and/or mitigation plans omitted. All plans in the submittal should reflect the removal of buildings out of the resource area, not just the site plan.
2. The SWPPP review is done concurrently with the Grading plan. Please resubmit the SWPPP along with the Grading review.
Floodplain Use Permit:
1. The FUP cannot be approved prior to the grading plan. Re-submit along with the grading plan.
Drainage Report:
1. Please submit a detailed response letter to the review comments along with the corrected copies of the DR.
2. Addendums to the DR are not accepted. The addendum must be incorporated into the original DR.
3. Revise all maps and reports to reflect the current changes shown on the site plan.
Stormwater pollution prevention plan:
1. The SWPPP review is done concurrently with the Grading plan. Please resubmit the SWPPP along with the Grading review. The SWPPP will be reviewed at time.

If you have any questions, I can be reached at 791-5550 x1193 or Paul.Machado@tucsonaz.gov
Paul P. Machado
Senior Engineering Associate
City of Tucson/Development Services Department
201 N. Stone Avenue
P.O. Box 27210
Tucson, Arizona 85726-7210
(520) 791-5550 x1193 office
(520) 879-8010 fax
C:/8526 E Tanque Verde Rd._Site 4
09/26/2005 DAN CASTRO ZONING HC SITE REVIEW Passed PASSED ON FIRST REVIEW 2/18/05