| Review Date | Reviewer's Name | Type of Review | Description | Status | Comments |
|---|---|---|---|---|---|
| 11/30/2005 | JIM EGAN | FIRE | REVIEW | Approved | |
| 11/30/2005 | ROBERT SHERRY | PLUMBING-COMMERCIAL | REVIEW | Denied | 1. The minimum font size shall be 1/8". 2. The specified water closet is illegal per ARS 45-313. 3. Show how the connection for the condensate drain shown on the soil & vent riser diagram complies with the 1994 UPC. 4. Clarify the size of the existing CW pipe to which the new spiping is being connected. It is shown as both 1" and 3/4". If it is 3/4", show the existing load it is serving. 5. Provide heat traps and pipe insulation for the water heater per Section 804, IECC 2003. 6. The water pressure calculations do not support using a 1/2" pipe to serve a water closet. 7. Show the "approved manner" for attaching the water heater to the wall structure. Note that the water heater is shown as being mounted "above ceiling" and at a maximum height of 5'-0". Please clarify. |
| 11/30/2005 | CHRISTY FOREMAN | BUILDING-COMMERCIAL | REVIEW | Denied | 1) Provide vertical grab bar per section 604.5.1 and 604.4.2. |
| 11/30/2005 | ROBERT SHERRY | WATER | REVIEW | Approved | |
| 11/30/2005 | ROBERT SHERRY | MECHANICAL-COMMERCIAL | REVIEW | Denied | 1. The minimum font size shall be 1/8". 2. Provide an auxiliary/secondary drain system for the fan coil unit. Reference Section 307.2.3, IMC 2000. 3. Show how EF-1 will be controlled to prevent recirculation of the air supplied to the restroom. Reference Section 403.2.1 (3), IMC 2000. 4. Provide duct insulation per Section 803.2.8, IECC, 2003. 5. The plumbing plan shows the condensate drain terminating outside the building. SHow that the termination point complies with Section 307.2.1, IMC 2000 as amended by the City of Tucson. |
| 12/01/2005 | LINDA BUCZYNSKI | ELECTRICAL-COMMERCIAL | REVIEW | Denied | T05CM05922 12/1/05 1. Provide a disconnect for the Water Heater per NEC 422 Part III. 2. Sheet A3 indicates WH is 4.5 KW. Only 1650 VA per panel schedule. Coordinate with Plumbing and clarify. 3. HPCU-1 with 36.3 FLA, shall not be on a 20A Ckt. 4. 1/0 panel feeder has 150A ampacity. Reference NEC Table 310.16. Not protected by a 200A CB. 5. Provide service load calculations. |
| 12/14/2005 | GBONILL1 | WWM | REVIEW | Needs Review | |
| 12/14/2005 | GBONILL1 | ZONING | REVIEW | Needs Review | |
| 12/14/2005 | GBONILL1 | ENGINEERING | REVIEW | Needs Review |